Azman HKL: Good morning.
1/2/2023. Site progress.
5th floor. Slab formwork in progress.
Azman HKL: 5th floor column. Casted.
Azman HKL: Ground floor. Slab rebar and M&E services installation in progress.
Azman HKL: Ground floor. Formwork in progress.
Azman HKL: Basement. Foundation casted.
Azman HKL: Basement pile cap foundation.
Azman HKL: Ground floor conduit installation
Azman HKL: Ground floor slab. M&E services target done 11am. Bossku @Kadapi J. HKL can comeand ready for joint inspection at 1.30pm.
+60 12-833 6147: 👍🏻
Azman HKL: Heavy rain on site.