Monday, January 30, 2023

31 JAN 23 HKL

Azman HKL: Good morning. 
31/01/2023. Site progress. Zone 1S. Ground floor slab. Rebar & M&E services in progress.
Azman HKL: Basement. Zone 2A/a. Foundation casted
Azman HKL: Basement zone 1D. Earthwork in progress.
Azman HKL: 6th floor. Slab formwork in progress
 Azman HKL: Basement zone 1 & 2. Slab formwork in progress.
Azman HKL: Lift pit opening inspection at ground floor Mall slab with Mitsubishi and consultant.











 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...