31 JAN 23 HKL

Azman HKL: Good morning. 
31/01/2023. Site progress. Zone 1S. Ground floor slab. Rebar & M&E services in progress.
Azman HKL: Basement. Zone 2A/a. Foundation casted
Azman HKL: Basement zone 1D. Earthwork in progress.
Azman HKL: 6th floor. Slab formwork in progress
 Azman HKL: Basement zone 1 & 2. Slab formwork in progress.
Azman HKL: Lift pit opening inspection at ground floor Mall slab with Mitsubishi and consultant.











 