Site progress. 3/10/2022
GL: F-H/8-11. 8.00am
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
EG MALL SITE DAILY ( 31 JULY 2025)
EG MALL NSC ( 11 MARCH 2025)
EG MALL NSC ( 11 MARCH 2025) [11/3/2025 10:26 AM] +60 16-837 8881: Belum habis naik bata tapi mahu paitong sudah ? 6th floor. Genset roo...
EG MALL NSC ( 6 MAY 2025)
EG MALL NSC ( 6 MAY 2025) Request for Inspection. 10am. Tower B. 16th floor. [6/5/2025 10:02 AM] Azman HKL: Consultant on the way to ins...
EGMALL COORDINATION (8/4/2025)
EGMALL COORDINATION (8/4/2025) 7M. Cooling tower, water tank. Plinth inspection. 7M. Done M&E inspection. Please proceed. @EG MALL Nasri