Monday, October 31, 2022
Sunday, October 30, 2022
31 OCT 22 HKL
SITE GROUP
Site progress. 31/10/2022
2nd floor
Lift pit
Basement watertank
Kadapi : Should have details of this through r.c. wall.
Kadapi : Please prepare details of punch trough r.c. wall.
AZMAN : @Joseph Wong KH please double check. Your soil and waste pipe dropper pipe from hotel outlet to Main hole. If any pipe sleeve thru basement wall.
Friday, October 28, 2022
29 OCT 22 HKL
SITE GROUP
GL: F-I/5-6. 2nd floor slab formwork in progress
Site progress. 29/10/2022. 1st floor mall. GL: F-I/7-11. Column in progress
Basement watertank area. Column n wall rebar in progress.
Lift pit formwork in progress
I/10 socket done installed.
Thursday, October 27, 2022
28 OCT 22 HKL
i/9 siap
Basement water tank, wall rebar in progress.
Lift pit wall rebar in progress
Site progress. 28/10/2022
1st floor, GL: F-I/7-11. Column in progress.
Subscribe to:
Posts (Atom)
EGMALL COORDINATION (26/6/2025)
EGMALL COORDINATION (26/6/2025) [26/6/2025 4:41 PM] Azman HKL: Consultant commented. DCC ada orang maw rectify ini ASAP. 👏 [26/6/2025 4:...

-
EG MALL NSC ( 11 MARCH 2025) [11/3/2025 10:26 AM] +60 16-837 8881: Belum habis naik bata tapi mahu paitong sudah ? 6th floor. Genset roo...