Friday, October 28, 2022

29 OCT 22 HKL

SITE GROUP

GL: F-I/5-6. 2nd floor slab formwork in progress

Site progress. 29/10/2022. 1st floor mall. GL: F-I/7-11. Column in progress

Basement watertank area. Column n wall rebar in progress.

Lift pit formwork in progress

I/10 socket done installed.

 

No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...