Wednesday, December 28, 2022

29 DEC 22 HKL

SITE GROUP
Azman HKL: Site progress. 29/12/2022.
5th floor.
Azman HKL: Bottom layer rebar
Azman HKL: Basement. Zone 2. Foundation rebar n earthwork in progress
Azman HKL: Zone 2. Foundation
Azman HKL: Basement zone 1D. Earthwork in progress.









 

Tuesday, December 27, 2022

28 DEC 22





 

28 DEC 22 HKL

NSC GROUP

Azman HKL: Site progress. 28/12/2022
5th floor.

Azman HKL: 4th floor. Column.

 Azman HKL: Basement. Zone 2 foundation rebar.


Azman HKL: Zone 2.



Azman HKL: Basement zone 1D. Pile cap L/7 t& L/8.

Azman HKL: For info. 5th zone 1 floor casting plan is on 31/12/2022. Saturday. NSC, please be informed. The bottom layer bar is expected to be ready on 29/12 so M&E services can start.


 