29 DEC 22 HKL
SITE GROUP
Azman HKL: Site progress. 29/12/2022.
5th floor.
Azman HKL: Bottom layer rebar
Azman HKL: Basement. Zone 2. Foundation rebar n earthwork in progress
Azman HKL: Zone 2. Foundation
Azman HKL: Basement zone 1D. Earthwork in progress.