Monday, November 28, 2022
Saturday, November 26, 2022
Friday, November 25, 2022
26 NOV 22 HKL
SITE GROUP
Azman HKL: Site progress. 26/11/2022 3rd floor slab. M&E installation
Azman HKL: 3rd floor rebar n slab inprogress
Azman HKL: Rebar in progress
Azman HKL: Basement water tank area
Azman HKL: Pile cap area dewatering.
Kadapi: Currant progress at level 3.
Azman HKL: Rebar installation in progress.
Azman HKL: Dear @Kadapi J.. DCC supervisor and rebar subcon had discuss that M&E items can complete by 9.30am tomorrow. So request for inspection tomorrow at 10am. I had informed my top management your OT given permission to proceed. 🙏🏿
NSC GROUP
Azman HKL: Please double check your item this area. Slab casting will proceed.👆
Thursday, November 24, 2022
25 NOV 22 HKL
SITE GROUP
Azman HKL: Basement watertank
Azman HKL: Basement pile cap
Kadapi: As i mention to KH b 4 regarding DP10. Please double check either it continuesly to the floor above or ended at level 2? Also the room size is it fit with our MnE or how? GL 5/I. Tq
NSC GROUP
Azman HKL: @Joseph Wong KH RFI for this pump sump opening..
Edwin: Architecture works also need M&E contractor to submit RFI?
Azman HKL: That pump sump opening to fit pump set M&E. For me better to submit RFI to check if any discrepancy of the drawing.