Friday, November 25, 2022

26 NOV 22 HKL

SITE GROUP
Azman HKL: Site progress. 26/11/2022 3rd floor slab. M&E installation
Azman HKL: 3rd floor rebar n slab inprogress

Azman HKL: Rebar in progress
Azman HKL: Basement water tank area

Azman HKL: Pile cap area dewatering.






Kadapi: Currant progress at level 3.


Azman HKL: Rebar installation in progress.

Azman HKL:  Dear @Kadapi J.. DCC supervisor and rebar subcon had discuss that M&E items can complete by 9.30am tomorrow. So request for inspection tomorrow at 10am. I had informed my top management your OT given permission to proceed. 🙏🏿


NSC GROUP
Azman HKL: Please double check your item this area. Slab casting will proceed.👆




 

26 NOV 22














 

Thursday, November 24, 2022

25 NOV 22 HKL

SITE GROUP
Azman HKL: Site progress. 25/11/2022 3rd floor conduit installation
Azman HKL: 3rd floor formwork

Azman HKL: Basement watertank

Azman HKL:  Basement pile cap
Kadapi: As i mention to KH b 4 regarding DP10. Please double check either it continuesly to the floor above or ended at level 2? Also the room size is it fit with our MnE or how? GL 5/I. Tq








NSC GROUP

Azman HKL: @Joseph Wong KH RFI for this pump sump opening..
Edwin: Architecture works also need M&E contractor to submit RFI?
Azman HKL: That pump sump opening to fit pump set M&E. For me better to submit RFI to check  if any discrepancy of the drawing.




 