Tuesday, May 2, 2023
Monday, May 1, 2023
02 MAY 23 HKL
SITE GROUP
Azman HKL: Good morning. Site picture progress. 2/5/2023.
Azman HKL: 2nd floor. Column rebar and formwork at ramp3 in progress. Beam rebar and slab formwork in progress.
Azman HKL: 2nd floor zone 4. Slab formwork in progress.
Azman HKL: Basement lift wall rebar in progress. 1st floor slab formwork and scaffolding support in progress.
Azman HKL: 1st floor slab formwork in progress.
Azman HKL: Ground floor. GL: D-F/10-11. Slab cast.
Azman HKL: Basement zone 5. Retaining wall formwork in progress. Column rebar in progress. lift wall rebar in progress.
NSC GROUP
Azman HKL: Basement. 7a+7b. Foundation slab rebar in progress.
Azman HKL: Chiller room.
Azman HKL: Basement. Brickwall in progress.
Azman HKL: Basement. Smoke spill room brick wall in progress.
Azman HKL: Today M&E coordination meeting. After the weekly subcon meeting.
Azman HKL: Mitsubishi on site to check the basement lift pit opening.
Subscribe to:
Posts (Atom)
-
EG MALL NSC ( 11 MARCH 2025) [11/3/2025 10:26 AM] +60 16-837 8881: Belum habis naik bata tapi mahu paitong sudah ? 6th floor. Genset roo...
-
EGMALL COORDINATION (22/4/2025) 0198218251(1.42PM) : Petang Azman, tolong pasang pintu untuk motor room di office block dekat tingkat 21....