Azman HKL: Good morning. Site picture progress. 2/5/2023.
Azman HKL: 2nd floor. Column rebar and formwork at ramp3 in progress. Beam rebar and slab formwork in progress.
Azman HKL: 2nd floor zone 4. Slab formwork in progress.
Azman HKL: Basement lift wall rebar in progress. 1st floor slab formwork and scaffolding support in progress.
Azman HKL: 1st floor slab formwork in progress.
Azman HKL: Ground floor. GL: D-F/10-11. Slab cast.
Azman HKL: Basement zone 5. Retaining wall formwork in progress. Column rebar in progress. lift wall rebar in progress.
NSC GROUP
Azman HKL: Basement. 7a+7b. Foundation slab rebar in progress.
Azman HKL: Chiller room.
Azman HKL: Basement. Brickwall in progress.
Azman HKL: Basement. Smoke spill room brick wall in progress.
Azman HKL: Today M&E coordination meeting. After the weekly subcon meeting.
Azman HKL: Mitsubishi on site to check the basement lift pit opening.