Wednesday, January 11, 2023

12 JAN 23
























 

12 JAN 23 HKL

SITE GROUP

 Azman HKL: Site progress. 12/01/2023
5th floor.
Azman HKL: 5th floor
Azman HKL: Basement, zone 2. Column and wall rebar in progress
Azman HKL: Basement zone 1D. Wall and column rebar in progress.
Azman HKL: Ground floor sanitary pipe in progress.


NSC GROUP
 Azman HKL: Dear all, Ground floor target casting date for Zone 1D/a on 28/01/23 and Zone A1 on 30/01/23, please follow this dates accordingly












 

11 JAN 23 HKL

NSC GROUP

Azman HKL: Site progress. 11/01/2023
5th floor.
Azman HKL: 5th floor slab
Azman HKL: Basement zone 2. Column rebar, wall rebar, earthwork in progress
 Azman HKL: Basement zone 1D. Casted. Column work will started.

Azman HKL: Basement zone 1. Earthwork in progress
Azman HKL: Ground floor. Sanitary pipe in progress.














 

EG MALL SITE DAILY ( 31 JULY 2025)