Azman HKL: Site progress. 11/01/2023
5th floor.
Azman HKL: 5th floor slab
Azman HKL: Basement zone 2. Column rebar, wall rebar, earthwork in progress
Azman HKL: Basement zone 1D. Casted. Column work will started.
Azman HKL: Basement zone 1. Earthwork in progress
Azman HKL: Ground floor. Sanitary pipe in progress.