Friday, January 6, 2023

07 JAN 23 HKL

SITE GROUP

Azman HKL: Site progress. 7/01/2023
5th floor.
Azman HKL: 5th floor. Slab rebar in progress.
Azman HKL: Basement zone 2. Housekeeping and earthwork
Azman HKL: Housekeeping in progress
Azman HKL: Basement zone 1D.  Slab rebar and earthwork in progress.










Thursday, January 5, 2023

06 JAN 23






 

06 JAN 23 HKL

SITE GROUP
Azman HKL: Site progress. 6/01/2023
5th floor. Column in progress
 Azman HKL: 5th floor. Slab rebar in progress
Azman HKL: Basement zone 2. Earthwork
Azman HKL: Basement zone 1D. Slab rebar and earthwork.






NSC GROUP
Edwin Chen 013: We will use this area to store our CI pipe @+60 13-555 1882
Azman HKL: Morning bos. We will check for you that area but can you write in a letter to HKL.
                       Specific area, date, material in store. I will check the area availability for you.
Edwin Chen 013: Letter already wrote in more than one week ago. @Raymond Chong. Y. F (HKL P.                                    Manager). Can you clarify this ?
Azman HKL: 👌noted. Will check with @Raymond Chong. Y. F (HKL P. Manager) .
Edwin Chen 013: Thanks
Azman HKL: Slab progress.





 

Wednesday, January 4, 2023

05 JAN 23 HKL

SITE GROUP
Azman HKL: Site progress. 5/01/2023
5th floor.
Azman HKL: 5th floor column in progress
 Azman HKL: 5th floor beam rebar and formwork
Azman HKL: Beam and formwork in progress
Azman HKL: Basement zone 2.
Azman HKL: Slab rebar and earthwork
Azman HKL: Basement zone 1D. Slab rebar and earthwork
Azman HKL: Slab rebar

NSC GROUP
Azman HKL: For info. 5th floor zone 2. GL: F-I/8-11. Casting plan on 9/01/2023. Next Monday. NSC, please be informed.



 

04 JAN 23



 

Monday, January 2, 2023

03 JAN 23 HKL

SITE GROUP
Azman HKL: Site progress. 3/1/2023
5th floor
Azman HKL: 5th floor slab formwork in progress
Azman HKL: Basement, zone 2. Rebar and earthwork in progress
Azman HKL: Basement zone 1D. Earthwork in progress.







 