Azman HKL: Site progress. 6/01/2023
5th floor. Column in progress
 Azman HKL: 5th floor. Slab rebar in progress
Azman HKL: Basement zone 2. Earthwork
Azman HKL: Basement zone 1D. Slab rebar and earthwork.






NSC GROUP
Edwin Chen 013: We will use this area to store our CI pipe @+60 13-555 1882
Azman HKL: Morning bos. We will check for you that area but can you write in a letter to HKL.
                       Specific area, date, material in store. I will check the area availability for you.
Edwin Chen 013: Letter already wrote in more than one week ago. @Raymond Chong. Y. F (HKL P.                                    Manager). Can you clarify this ?
Azman HKL: 👌noted. Will check with @Raymond Chong. Y. F (HKL P. Manager) .
Edwin Chen 013: Thanks
Azman HKL: Slab progress.





 