Monday, December 5, 2022
06 DEC 22 HKL
SITE GROUP
Azman HKL: Site progress. 6/12/2022 4tg floor slab formwork inprogress
Azman HKL: 4tg floor formwork
Azman HKL: 3rd floor column rebar
Azman HKL: Column rebar
Azman HKL: Basement walk rebar inprogress
Azman HKL: Pile cap area
Azman HKL: Zone 2 area. Earthwork inprogress
Azman HKL: 3rd floor column. F/9 , I/9 & I/11 socket box installation by DCC inprogress.
Sunday, December 4, 2022
Friday, December 2, 2022
03 DEC 22 HKL
SITE GROUP
Azman HKL: 3rd floor rebar tie and cleaning
Azman HKL:3rd floor column
Azman HKL: 4th floor beam and slab formwork
Azman HKL: Basement wall rebar and formwork
Azman HKL: Pile cap area
Azman HKL: L/6 pile cap
Kadapi: The opening for pump sum pipes and the other opening or pipe sleeve not yet install?
Kadapi: Tje heights, size and the position?
Lo. W.H (HKL-Site Engineer) :Its at higher level than we cast
Kadapi: I haven't see any detail of it?
Lo. W.H (HKL-Site Engineer) : HKL have issued shop drawing To Promes
Kadapi: Let me see it lah so that we can addjust on site if needed.
NSC GROUP
Azman HKL: Casting plan for 4th floor. 👆. NSCs please address any issue early. Such as drawing and others. Inform early if any. 🙏
Thursday, December 1, 2022
02 DEC 22 HKL
SITE GROUP
Azman HKL: Site progress, 2/12/2022, top rebar and column inprogress
Azman HKL: Column inprogress and 4th beam formwork inprogress
Azman HKL: Basement wall rebar and plinth formwork inprogress.