03 DEC 22 HKL

SITE GROUP
Azman HKL: 3rd floor rebar tie and cleaning

Azman HKL:3rd floor column

Azman HKL: 4th floor beam and slab formwork

Azman HKL: Basement wall rebar and formwork
Azman HKL: Pile cap area

Azman HKL: L/6 pile cap

Kadapi: The opening for pump sum pipes and the other opening or pipe sleeve not yet install?
Kadapi: Tje heights, size and the position?
Lo. W.H (HKL-Site Engineer) :Its at higher level than we cast
Kadapi: I haven't see any detail of it?
Lo. W.H (HKL-Site Engineer) : HKL have issued shop drawing To Promes
Kadapi: Let me see it lah so that we can addjust on site if needed.


NSC GROUP

Azman HKL:  Casting plan for 4th floor. 👆. NSCs please address any issue early. Such as drawing and others.  Inform early if any. 🙏



 