RAYMOND: Econmech, these pallets no need to remove? When can u remove them and let us rectify the plinths edges?
DART: nt sy atur bos

BONAVENTURE: Pipe boleh atur kasi pindah mo buat level peg mall podium

RAYMOND: Dart, sini bila mau jalan pipe?
[9/6/2025 9:17 AM] EG MALL ECONMECH Dart: sedang plan lukis kasi cantik
[9/6/2025 9:17 AM] EG MALL ECONMECH Dart: double decker pipe. tu fin sy sdh mnta jsk hold sana
[9/6/2025 9:17 AM] +60 12-559 6863: Bila bolih jalan?
[9/6/2025 9:18 AM] EG MALL ECONMECH Dart: dlm 2 mggu lagi la bos. sy design bracket and support lg
[9/6/2025 9:19 AM] +60 12-559 6863: Design perlu 2 minggu kah?
[9/6/2025 9:19 AM] EG MALL ECONMECH Dart: mau buat support tu bos c Channel
[9/6/2025 9:19 AM] +60 12-559 6863: Sudah 2 minggu kita bincang masi perlu 2 minggu lagi?
[9/6/2025 9:21 AM] EG MALL ECONMECH Dart: steady ba bos. compressor pun baru saja naik
[9/6/2025 9:21 AM] EG MALL ECONMECH Dart: nt sy expedites kerja saya d atas
[9/6/2025 9:25 AM] +60 14-379 2990: Okay boleh..
[9/6/2025 9:25 AM] +60 12-559 6863: Pasti ya

BONAVENURE: Tower B lvl 8 unit 5 & 6 Aircon drain pipe atur tutup lobang


Site progress photo.
9/6/2025.
Tower A.

Tower A. Upper roof floor. Roofing structure in progress.

7th floor and mezanine floor.

Tower B.
18th floor. Slab cast.
18th floor. Slab/wall panel
17th floor..wall rebar and panel.

Tower B. 18th floor.

Tower B. 18th floor.


No comments:

Post a Comment

EGMALL COORDINATION (26/6/2025)

   EGMALL COORDINATION (26/6/2025) [26/6/2025 4:41 PM] Azman HKL: Consultant commented. DCC ada orang maw rectify ini ASAP. 👏 [26/6/2025 4:...