EG MALL NSC ( 5 JUNE 2025)
Site progress photo.
5/6/2025
Tower A.
21st floor. Tower A. Pyramid roof in progress
7th floor. Cooling tower Water tank setup.
Tower B.
18th floor. Slab rebar, panel and M&E works.
17th floor. Wall rebar and M&E works.
18th floor. Tower B.
18th floor. Tower B
17th floor. Tower B
JIMMY: @HIDAYA KH office Num level 7 siap pindah scaffolding
[5/6/2025 12:18 PM] Edwin Chen 013: I believe it would be a more effective approach to design and implement a movable scaffold. This solution would provide greater flexibility. Additionally, it would significantly improve overall efficiency by reducing setup time and enabling quicker repositioning, ultimately contributing to a faster and more streamlined workflow.
[5/6/2025 12:23 PM] Jimmy HKL: For your info today scaffolder inspector will come to site for design mobile scaffolding this area.
JIMMY: @~Leppong @HIDAYA KH office Num @~WY𫨠Esok 06.06.2025 (Jumaat) bagi 2 org untuk gotong royong housekeeping level 7 pada jam 10 pagi. Gagal untuk bagi kerjasama saman akan menyusul.
[5/6/2025 3:00 PM] +60 10-809 0001: @Jimmy HKL atur housekeeping gotong royong d airwell Tower B juga level 8-11. As per sub con meeting on Tuesday
[5/6/2025 3:01 PM] Jimmy HKL: okay bos
[5/6/2025 3:01 PM] +60 10-809 0001: šš¼
@Edwin Chen 013 Untuk makluman scaffolder inspector En.Mazlan telah beri penerangan berkaitan pemasangan mobile scaffolding untuk tingkat 7 dan tiada halangan untuk pemasangan tersebut.
18th floor. Tower B. Pre inspection M&E services.
18th floor. Tower B.
Tower B. 8th floor. Joint inspection hosereel riser room