EG MALL NSC ( 28 MAY 2025)

   EG MALL NSC ( 28 MAY 2025)

raymond: Econmech, L13 sudah tengah tutup ceiling board, kerja ko belum siap lepas lebih kurang 1 bulan sudah
[28/5/2025 8:51 AM] +60 12-559 6863: @EG MALL ECONMECH Dart please answer
[28/5/2025 8:54 AM] +60 14-379 2990: On going.. orang kami start sudah pasang.
Morning, minta tolong plaster area sini.. fan room 

@Azman HKL @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘”

[28/5/2025 9:02 AM] +60 19-895 9900: @Azman HKL pagi bossku, as per last week mtg we & consultant has request HKL to hand over 6th floor all Plant room to DCC for preparation of energizing Tower A Hotel & Office, next week our Genset installer wil go full swing install & swisgears wil arrived site  for final installation/termination, ur attention is highly needed tq
[28/5/2025 9:13 AM] Azman HKL: Ok thanks inform. πŸ‘

azman: 6th floor. Genset room

azman: 6th floor. Genset room. @Debra S. HKL Please follow-up Subcon immediately start floor screeding inside Genset room. We hand over the room to DCC.

lo keam: @Azman HKL 6th floor Consumer HV swis room





Genset room acoustic door finishing

lo keam: Fire door blm pasang
azman: @~LO KEAM saya sama Eddy baru dari sana tadi. Bagus kita cek sama2 tadi. Kami atur itu screeding dalam bilik Genset.

lo keam: 6th floor MSB room bata blm siap
[28/5/2025 11:04 AM] Azman HKL: Dalam itu bilik kami inform sama subcon untuk repair.
[28/5/2025 11:05 AM] Azman HKL: Ini kami sudah bincang di site sama Eddy, saya tidak kejar itu bata sebab, maw pasang cable tray sama busduct.
[28/5/2025 11:05 AM] Azman HKL: Tapi kalau maw cepat, saya kejar itu subcon bata ya.
[28/5/2025 11:06 AM] +60 19-895 9900: Ok bah bossku, just gentle reminder, buat aje ape yg perlu tqπŸ‘ŒπŸ»πŸ‘ŒπŸ»πŸ‘ŒπŸ»πŸ™πŸ»πŸ™πŸ»πŸ™πŸ»
[28/5/2025 11:06 AM] Azman HKL: Iya. TQ reminder ngam tu. πŸ‘ŒπŸ‘ŒπŸ‘πŸ‘. Sama2 kerja.


[28/5/2025 11:40 AM] Azman HKL: @~WY🫨 tolong cek. Ducting di SPD. ST4 dan ST7.
[28/5/2025 11:41 AM] Azman HKL: ST4, kamu sudah inform tiada sudah extend kan. Itu boleh tutup.

Site progress photo.
28/5/2025
Tower A.

Tower A. 21st floor. Lifting water tank panel and equipment.

7th floor. Mezanine. Water tank panel.

Tower B.
18th floor. Slab/wall panel 
17th floor. Wall reba

Basement. Earthwork in progress


[28/5/2025 5:09 PM] Azman HKL: Daily report. Ini minggu. 
@HIDAYA KH office Num @~s4yamahuk4ya88.gmail.com @~WY🫨 @~zee πŸ‘πŸ‘πŸ‘
[28/5/2025 6:27 PM] +60 12-843 3877: Esok lah