Friday, June 13, 2025

EGMALL COORDINATION (6/6/2025)

  EGMALL COORDINATION (6/6/2025)

18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation.

18th floor. Tower B


18th floor. AC drain pipe


EGMALL COORDINATION (5/6/2025)

    EGMALL COORDINATION (5/6/2025)

Tower B. 8th floor. Staircase 3. Joint inspection for Hosereell riser room. @HIDAYA KH office Num @~s4yamahuk4ya88.gmail.com @~zee @~WY🫨 


8th floor. Tower B.

Tower B. 18th floor. Pre Inspection M&E services.



EGMALL COORDINATION (27/5/2025)

   EGMALL COORDINATION (27/5/2025)



AZMAN: Joint inspection. Consultant, DCC, SESB contractor.


EG MALL NSC ( 13 JUNE 2025)

  EG MALL NSC ( 13 JUNE 2025)







EG MALL NSC ( 12 JUNE 2025)

 EG MALL NSC ( 12 JUNE 2025)



[12/6/2025 8:29 AM] +60 12-559 6863: @Azman HKL @walker mari L15 lift lobby sekarang, ada mau bincang
[12/6/2025 8:29 AM] Azman HKL: Ok. πŸ‘Œ


2nd floor. Floor screeding in progress. @~s4yamahuk4ya88.gmail.com @~zee tolong saya cek ya. Mana2 obstruction kamu punya services. Saya tidak dapat bantu kalau kamu tidak inform sama saya. πŸ‘πŸ‘
MAKLUMAN

Hari ini 12.06.2025 (Khamis) pihak HSE akan adakan gotong royong housekeeping level 8 Tower B pada jam 10 pagi. Sila hantar pekerja anda 2 org untuk menjayakan program ini dan sekiranya gagal untuk bagi kerjasama saman akan menyusul. Mohon bagi kerjasama terima kasih. @HIDAYA KH office Num @~Leppong @~zee @~WY🫨
Tower A. Lift lobby. 14th to 20th.  Ceiling works setup and installations in progress. Please expedite all services above ceiling. Take priority and inform me any obstacle to install. πŸ‘πŸ‘. @EG MALL ECONMECH Dart @~LO KEAM @HIDAYA KH office Num @~zee .

LOH: Ikut aje simpan point di construction dwgs kolo ada






[12/6/2025 8:50 AM] +60 16-837 8881: Lv14 lama lagi boleh siap kerja kami sini pasal MSB office di sana ......
Busduct belum confirm , feeder sesb belum pasang
[12/6/2025 8:52 AM] Azman HKL: Kalau perlu masa tolong inform memo atau letter ya.  πŸ‘. Nanti saya keluar surat untuk kerja2 pemasangan ceiling di lift lobby untuk reference kita. πŸ‘Œ
[12/6/2025 8:59 AM] +60 19-895 9900: Bossku, ni bahagian tak buli jalan ceiling dulu, busduct blm selesai, masi tunggu client & consultant punya desition

14th floor. Kita kasi tinggal ceiling area untuk pasang kerja pasang Busduct. Ada lain masalah tolong inform..πŸ‘. @~s4yamahuk4ya88.gmail.com akan inform tempat perlu buka on site.




EG MALL NSC ( 11 JUNE 2025)

   EG MALL NSC ( 11 JUNE 2025)

BONAVENTURE: @HIDAYA KH office Num ini sdah grout boleh kasi cement rata sama slab lvl 8 unit 5 tower B
AZMAN: okay boleh

AZMAN: Tower A. 21st floor. @~WY🫨 tolong cek dia. Kalau siap pasang pipe sleeve dan tutup dia bagus.

BONAVENTURE: @HIDAYA KH office Num ada rectification work cni.waterproof sya tidak dapat buat unit 13

[11/6/2025 11:17 AM] HIDAYA KH office Num: ya. hold dulu tu 1 unit
[11/6/2025 11:17 AM] +60 14-654 4699: Ok

AZMAN: 14th floor. Tower A. Lift lobby. ceiling bar in progress. All M&E above ceiling please check again..any outstanding please install or inform me. @~WY🫨 @~s4yamahuk4ya88.gmail.com @~zee @HIDAYA KH office Num 

AZMAN: All pipe sleeve or opening please seal off before ceiling. πŸ‘
S4YAMAHUK: Kami punya banyak lagi di sana ya
Submain cable belum jalan lagi sebab belum conform 

Basduct sana juga mau lalu ke MSB ROOM Level 14_ juga belum conform

BONA: @HIDAYA KH office Num cuba check apa masala ni lvl 9 unit 27 tandas

[11/6/2025 2:36 PM] HIDAYA KH office Num: okay2


[11/6/2025 3:01 PM] Azman HKL: Tower B. 9th floor. @~WY🫨 tolong kasi naik dan tutup lubang. Ini nampak macam ke bawah siling. πŸ‘
[11/6/2025 3:02 PM] Azman HKL: Tolong cek ya..semua tempat pun sama. macam 8th floor tu ok.
[11/6/2025 3:12 PM] +60 14-379 2990: Noted.



Tower A. 21st floor. VRV setting out works.





External works. PN10 pipe for SESB incoming cable works




















EG MALL NSC ( 10 JUNE 2025)

  EG MALL NSC ( 10 JUNE 2025)

[10/6/2025 9:02 AM] +60 16-837 8881: @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” ini berapa kali sudah bukan lagi 1st time ......
[10/6/2025 9:08 AM] +60 16-837 8881: Ada org main main di site kasih masuk besi dalam pipe masa di slab ......
[10/6/2025 9:10 AM] +60 12-559 6863: Ini kali pertama saya terima complain dari kamu
[10/6/2025 9:17 AM] +60 16-837 8881: Ya
Biasa kami ni cuba settle di site dulu , tapi ni masala 3 kali sudah so saya minta tolong u sini

BONAVENTURE: @HIDAYA KH office Num ni unit 12 tinggal pu kan
[10/6/2025 9:22 AM] HIDAYA KH office Num: yaa
[10/6/2025 9:25 AM] +60 14-654 4699: Ni belum Seattle lagi sya mo atur waterproof masuk
[10/6/2025 9:28 AM] +60 19-895 9900: Buli minta lokasi di mana ni?

[10/6/2025 9:42 AM] +60 16-837 8881: SS Lv16
[10/6/2025 9:45 AM] Azman HKL: Okay thanks. Will check at site. Saya maw cari susah itu orang. Itu sebab kita sama2 maw inform saja. Kalau ada nampak itu org yang kasi masuk kasi tau. @EG MALL Nasri tolong juga ya. πŸ‘
[10/6/2025 9:50 AM] Azman HKL: Kalau nampak ini kes, terus inform saya. Baru saya dapat ambil tindakan. @~s4yamahuk4ya88.gmail.com nanti highlight ini dalam site meeting ni hari. Maw kasi rekod dia. TQ. πŸ‘

@~LO KEAM ada update shop drawing electrical di Mall? Kalau dapat kita maw coordinate sama ELV di site untuk kiosk. Sebab itu wall plastering dan floor screeding sedang jalan. 

2nd floor mall.


HIDAYAH: done wc installation. boleh kunci suda boss @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” 
[10/6/2025 11:29 AM] +60 12-559 6863: kena pintu kah?
[10/6/2025 11:29 AM] +60 12-559 6863: terus pasang
[10/6/2025 11:29 AM] HIDAYA KH office Num: kena
[10/6/2025 11:30 AM] +60 12-559 6863: ok, esok jam 1.30pm kita site walk sama ID dan architect, kau ikut la
[10/6/2025 11:32 AM] HIDAYA KH office Num: okay boleh boss
[10/6/2025 11:40 AM] +60 12-559 6863: ini memang sudah tau, mau pasang wall stopper nanti
[10/6/2025 11:40 AM] +60 12-559 6863: IF akan kasi idea




Plastering done ya.. @~Bonaventure 


EGMALL COORDINATION (26/6/2025)

   EGMALL COORDINATION (26/6/2025) [26/6/2025 4:41 PM] Azman HKL: Consultant commented. DCC ada orang maw rectify ini ASAP. πŸ‘ [26/6/2025 4:...