EG MALL NSC ( 16 MAY 2025)

    EG MALL NSC ( 16 MAY 2025)






AZMAN: SESB turnkey have done the pipe cast. @~LO KEAM @~Leppong make sure, to do good compaction of the road during backfill. The soil has been compacted before. We want to avoid the truck sinking due to the soft soil. 👏👏
[16/5/2025 5:31 PM] Azman HKL: Please reach the HKL Project Manager if needed site machinery.👏
[16/5/2025 5:32 PM] +60 10-809 0001: Apa isu tu? Who need machinery?
[16/5/2025 5:53 PM] Azman HKL: Sorry. Driving. Just to inform NSC if they needed HKL site machinery must reach for project Manager for approval.👏
[16/5/2025 5:56 PM] +60 10-809 0001: Ok, all works pls plan properly. Can inform 1-2 days in advanced. Ad hoc request will be as per availability basis. Tq