EGMALL COORDINATION(23/1/2025)
@Edwin Chen 013, @HIDAYA KH office Num & @Azman HKL, do we have Any pipe sleeve in r.c. beam here? If any please proceed. Tq
[23/1/2025 9:57 AM] +60 12-559 6863: Dear all, we will CJ this area above ramp and cast tomorrow
[23/1/2025 10:05 AM] EG MALL Mr Lo: Ok
[23/1/2025 11:59 AM] EG MALL Nasri: Sir CJ at this area no need we need to continue only CJ flushing at the beam sirš«”
[23/1/2025 12:00 PM] +60 12-559 6863: Bincang sama Lo dan buat apa yg patut
[23/1/2025 12:02 PM] EG MALL Nasri: Suda sir š«” and now beam and slab formwork rebar in progress suda sir


No comments:
Post a Comment