EG MALL NSC ( 8 MARCH 2025)
AZMAN HKL
Site progres photo.
8/2/2025
Tower A.
Tower A. Roof floor. Brick work in progress
Tower A. 21st floor.
7th floor. Mezzanine staging in progress.
6th floor. Genset room. Setting out work platform.
Tower B. 
14th/13th  floor. Slab/wall panel in progress.
13th floor..slab rebar, panel and M&E.
Tower B. 14th floor.
Tower B. 13th floor. Wall rebar
Tower B. 13th floor.
Tower A. 21st floor. Lift motor room. All equipment had been lifting into the room.
[8/3/2025 2:50 PM] +60 12-559 6863: so can we close up the
brick wall on Monday?
[8/3/2025 2:51 PM] Azman HKL: Brick wall can proceed. Have
inform Hassanal to proceed the brick wall.👌
[8/3/2025 2:51 PM] +60 12-559 6863: 👍
[8/3/2025 3:14 PM] +60 19-895 9900: @~YoonYK bro, pls ready
ur panel and show us the location on site for us to plan our submain tq
[8/3/2025 3:18 PM] +60 19-821 8251: Sure, once i ready the
panel will let you know. Later i send you the drawing also. 👌










 
 
 
 
 