EG MALL NSC ( 19 MARCH 2025)
[19/3/2025 9:24 AM] Azman HKL: Joint inspection with consultant. 10am. Zone 7m. Mezzanine floor. @~WY 👌
[19/3/2025 9:28 AM] EG MALL Mr Lo: @Edwin Chen 013 @HIDAYA KH office Num please place all the necessary flow trap
[19/3/2025 9:28 AM] EG MALL Mr Lo: pipe
[19/3/2025 9:29 AM] EG MALL Mr Lo: and also the opening pipe 50mm dia and 100mm dia punching through beam one
[19/3/2025 9:29 AM] EG MALL Mr Lo: thanks
[19/3/2025 9:31 AM] Edwin Chen 013: Please give location of the pipe sleeve. I don't want to have argument later.
Azman HKL: As Site per-discussion, proposed plinth adding 400mm height for cooling tower condenser pipe Installations and services due to structure design changes.
[19/3/2025 11:03 AM] +60 12-559 6863: Azman, get Promes to write to WHG for this, let engineer study the loading
[19/3/2025 11:24 AM] Edwin Chen 013: Please issue the work order before we proceed with the job. It’s important to have all documents in order to prevent any potential issues later. Additionally, I do not consider WhatsApp communication as a formal instruction method.
[19/3/2025 12:29 PM] EG MALL Mr Lo: Dear all,
14th floor, g/l 5-7 tower B cast tomorrow-20/3
7m th floor, g/l 9-16/K-L + 11-12/J-K the day after tomorrow-21/3
[19/3/2025 1:00 PM] EG MALL Mr Lo: In view of the urgency, our qs will issue the work order, at the mean time please install the ft piping first, we plan to cast the 7m 21/3/2025 Friday
[19/3/2025 1:01 PM] EG MALL Mr Lo: thanks 🙏 @Edwin Chen 013
[19/3/2025 1:03 PM] Edwin Chen 013: Thank you very much for your prompt execution and clear understanding of this matter.
[19/3/2025 2:18 PM] Azman HKL: @~Leppong @~zee @~WY @HIDAYA KH office Num please take note the cast date. 👏
[19/3/2025 2:36 PM] HIDAYA KH office Num: okay azman
[19/3/2025 3:08 PM] Azman HKL: Am on it. Will refer the detail with Econmech and write to Promes and WHG.