[7/1/2025 10:23 AM] Azman HKL: Masih kagi ka? Tadi org saya
pg cek di atas.
[7/1/2025 10:42 AM] Edwin Chen 013: Who is carrying out work
on the upper floor involving throwing water into the floor drain? This is not a
good practice, as it can lead to blockages in our pipes. Cement debris stuck
inside the pipe will cause serious issues and make clearing it extremely
difficult.
[7/1/2025 10:50 AM] Edwin Chen 013: It’s better to take
precautions and address this issue now rather than dealing with bigger problems
later.
[7/1/2025 10:55 AM] Azman HKL: 13th floor. Archi works. Will
issue a memo to the subcontractor. @~Debra S. @~π
πΆπ ππ½πππ
for info. Please confirm and inform the
subcontractor. ππ

[7/1/2025 12:03 PM]
Azman HKL: Please be informed of today's coordination meeting at 2pm.
[7/1/2025 1:21 PM] HIDAYA KH office Num: @Azman HKL room 3&4 lagi.
[7/1/2025 1:27 PM] Edwin Chen 013: No action being taken?
[7/1/2025 1:36 PM] +60 12-559 6863: already informed
waterproofing subcon, they will stop and clear
[7/1/2025 1:38 PM] +60 12-559 6863: maybe is the tangka
overflow, let us check 1st
[7/1/2025 1:45 PM] Edwin Chen 013: I’m concerned that the
workers might take a shortcut by pouring cement, sand, or water into our pipe.
This could cause significant blockages