Sunday, January 5, 2025

EGMALL NSC ( 3 JAN 2025)

  EGMALL NSC ( 3 JAN 2025)

@Azman HKL @~Leppong we need to plan this machine for transfer at the proper area, its because we need to clearing this area for next area we want to install shoring support beam and slab

Our CJ for the shoring support we dont yave any spacing already that why plss take action accordingly thank you 

[3/1/2025 9:43 AM] +60 16-837 8881: Morning

Pasal ini case , kita sudah perna ada discussion bilang bilik genset and TX room ready then we move in terus.....

[3/1/2025 9:46 AM] +60 12-559 6863: Shawn, the rooms will not complete if u don't shift, as we discussed earlier on, after we cast the cinema area, shift your equipment to below slab for our remaining area cast then only will the rooms be completed

[3/1/2025 9:46 AM] +60 12-559 6863: please coordinate at site and do what is necessary



 [3/1/2025 10:01 AM] +60 12-559 6863: tanya saya balik? kan Nas kata ko orang sudah bincang?

[3/1/2025 10:04 AM] Azman HKL: Sudah agree dalam meeting kan bos. Siap itu lantai, clear scaffolding, baru DCC masuk equipment.

[3/1/2025 10:05 AM] Azman HKL: Ini saya tidak faham. @EG MALL Nasri minta apa disini?



 [3/1/2025 10:10 AM] Azman HKL: @~Leppong minta tolong jumpa @EG MALL Nasri di sana. Minta apa yang perlu. Nanti saya turun bawah.

[3/1/2025 10:11 AM] +60 17-866 0355: Ok man

[3/1/2025 10:13 AM] +60 12-843 3877: Ya itu hari sudah bincang

Siap itu lantai baru tolak masuk itu equipment