[25/9/2024 9:10 AM] Azman HKL: Ok. Atur wall coring cepat. @+60 16-837 8881 💪💪
[25/9/2024 9:11 AM] +60 12-559 6863: Sudah Chuang approved kah? WHG tau tak? Kita terima itu pipe sleeves plan dari DCC kelmarin, mau submit kepada WHG dulu

[25/9/2024 9:15 AM] +60 12-559 6863: 7F depan pintu masuk tandas

[25/9/2024 9:19 AM] Azman HKL: Tunggu reply WHG kalau begitu. Terima verbal saja dari IR Chuang sama Jackson.

[25/9/2024 9:20 AM] +60 12-559 6863: Jackson sudah tau kah?

[25/9/2024 9:20 AM] +60 12-559 6863: Confirm satu kali sama dia

[25/9/2024 9:20 AM] Azman HKL: Kelmarin sda jackson check dimension onsite..

[25/9/2024 9:21 AM] Azman HKL: Dia ok..

[25/9/2024 2:11 PM] Azman HKL: Kinnangland will adjust on site based on site condition.