EGMALL NSC(27/7/2024)
[27/7/2024 8:41 AM] Azman HKL: 3rd floor. Ramp 5. Slab rebar and M&E in progress. Zone 8. Slab rebar in progress.
[27/7/2024
8:08 AM] Azman HKL: Morning. @+60 14-379 2990 nanti report ni progress slab
closing pagi ya. Maw hand over bagi sama team slab screeding. π. |
[27/7/2024
8:12 AM] Azman HKL: @+60 12-843 3877 atur siap ni wall hari ni. Buat proper
kualiti punya. π. Kita tidak maw Archi reject dan
HKL repair dan backcharge. 2 kali kerja. ππ. |
[27/7/2024
8:56 AM] +60 14-379 2990: Plastering work in progress level 8 to level 13
@Azman HKL |
[27/7/2024
9:00 AM] Azman HKL: Ok. Semua di 8th floor tu ya. Mana yang boleh tutup.
Kalau ada masalah inform saya, kita cari kasi selesai dia. π |
[27/7/2024
9:05 AM] Azman HKL: Strong reminder untuk kita semua: Site supervisor tolong
pantau kualiti kerja. Kualiti kualiti kualiti... |
[27/7/2024
9:07 AM] +60 12-559 6863: πͺπͺπͺ |
[27/7/2024
11:06 AM] Azman HKL: 15th floor. @+60 12-843 3877 kasi atur terus ni lubang
ya. |
[27/7/2024
11:09 AM] Azman HKL: 15th floor. Riser room. Tolong plaster bilik riser room
supaya boleh jalan paip. @EG Mall Shafee |
[27/7/2024
11:13 AM] Azman HKL: 15th floor. Toilet wall plastering in progress. |
[27/7/2024
11:23 AM] +60 12-843 3877: Level 15 opis sudah rectify |
@Azman
HKL |
[27/7/2024
11:26 AM] Azman HKL: Lift motor room. @+60 19-821 8251 . Confirm me. Kamu
tunggu tutup lubang wall, slab screeding dan itu wall plastering. |
[27/7/2024
11:27 AM] Azman HKL: TQ. Lepas ni, lepas buka terus tutup ya. Jangan biar
lama2.. kualiti maw jaga nuga. Jangan cincai tutup. Kita buat cantik2 sampai
puas hati semua.. |
[27/7/2024
11:44 AM] EG Mall Shafee: Ok… |
[27/7/2024
11:52 AM] Azman HKL: 9th floor. Please make it good. Wall surface not even.
Konsultan also cant accept. @+60 12-843 3877 π |
[27/7/2024
11:54 AM] +60 19-821 8251: Seal opening untuk machine beam, screeding and
motor room door |
[27/7/2024
11:55 AM] Azman HKL: Wall opening patching in progress. πͺπͺπ |
[27/7/2024
11:56 AM] Azman HKL: ELV conduit |
[27/7/2024
12:06 PM] +60 12-843 3877: π |
[27/7/2024
12:25 PM] Azman HKL: @+60 12-843 3877 @+60 11-6219 0511 @+60 14-379 2990 ini
ulang kali kita reminder. Tolong ya ya housekeeping. LSK saya tahu hari2 dia
ada gambar kerja housekeeping dia. Yang lain2 tolong. Semua M&E kena
bising. |
[27/7/2024
12:26 PM] Azman HKL: Ini atur dia sana hotel. |
[27/7/2024
12:26 PM] Azman HKL: ππ |
[27/7/2024
12:27 PM] +60 12-559 6863: Azman, tidak perlu inform lagi, hantar orang kita
kasi buat dan back charge saje |
[27/7/2024
12:37 PM] +60 16-837 8881: Ya Azman , tapi confirm gambar masa lepas kerja ,
ini masa sedang kerja sampah saya mesti ada , tapi setiap hari jam 4 lebih
saya akan kumpur semua sampah dan buang kalau boleh |
[27/7/2024
12:46 PM] +60 16-837 8881: Org saya memang sedang buat tadi kan ? |
[27/7/2024
1:04 PM] +60 16-837 8881: Saya urus terus kereta surung dan buang , kalau
karung karung banyak cerita |
[
[27/7/2024
1:06 PM] HIDAYA KH office Num: NSC- KH- Daily Manpower
[27/7/2024 1:58 PM] +60 12-843 3877:
Rectifycatioin _done
[27/7/2024 1:58 PM] +60 12-843 3877:Level 9 hotel unit Rectifycatioin _done @Azman HKL
[27/7/2024
2:00 PM] EG Mall Shafee: Turun pegi level 8
[27/7/2024
2:01 PM] EG Mall Shafee: Mock up room…
[27/7/2024
2:02 PM] Azman HKL: Terima kasih Raman. Pastikan semua ya kasi rata dia sebelum
wall skim.π
[27/7/2024
2:07 PM] Azman HKL: @+60 12-843 3877 @+60 17-866 0355 tolong dulu minta orang
kamu yang di 8th floor pg tgk dari mana itu air? π
[27/7/2024
2:14 PM] HIDAYA KH office Num: king hong corring di level 9. pastu kena conduit
dalam slab. pastu air tu keluar ikut junction box
[27/7/2024
2:15 PM] Azman HKL: Owh ok. @+60 17-866 0355 @+60 12-843 3877 tgk kalau masih
pakai. Kalau tdk, kasi tutup saja. Runding sama @HIDAYA KH office Num . Settle
dia di site saja.π
[27/7/2024
2:17 PM] +60 17-866 0355: @ok nanti sa cek@@Azman HKL
[27/7/2024
3:29 PM] +60 12-843 3877: Dcc Daily Report _work Progress
@8
th floor _hotel unit
Inspection
forwall
@hotel
9 th floor by dcc
Hacking
works @10 &15 floor
Running
trunking
@hotel
unit_level 8&9
Hacking
& rectifycatioin works
@8&9th
floor
[27/7/2024
4:10 PM] Azman HKL: Sample unit. Waterproofing will start on tuesday. Please
get all the work done. After
waterproofing no more coring and hacking. π