Saturday, June 8, 2024

8 JUN 2024 HKL

 SITE EG MALL

[14:21, 08/06/2024] +60 16-832 2597: Tower A 9F corridor wall level pegs inspection



[15:02, 08/06/2024] +60 16-832 2597: 8F Tower A sample rooms aluminium subframe inspection

[15:11, 08/06/2024] +60 12-843 3877: Insulation Mega test @level 3 in progress




NSC GROUP

[08:55, 08/06/2024] Azman HKL: Site progress photo. 
8/6/24.

[08:55, 08/06/2024] Azman HKL: 7th floor. TB6. Slab rebar and M&E in progress.

[08:55, 08/06/2024] Azman HKL: 3rd floor. Z8. Lab formwork and beam rebar in progress.

[08:57, 08/06/2024] Azman HKL: External area. Excavation and laying HDPE PN10 pipe works in progress.

[08:59, 08/06/2024] Azman HKL: Mitsubishi subcon to install lift door opening for safety precaution on site.
[08:59, 08/06/2024] +60 19-821 8251: Please help me follow up the clearance of debris in front of lift lobby also ya, thank you πŸ™
[09:02, 08/06/2024] Azman HKL: 8th floor. Hotel riser room. Unit 20&21. Toilet Exhaust Ducting in progress.


[09:31, 08/06/2024] +60 14-379 2990: @~Roxas Ng (Kai) @Azman HKL .. minta tolong buka ikut marking.. kami mahu jalan ducting..

[10:01, 08/06/2024] EG MALL ECONMECH Dart: Ni L14 riser duct. Kamu plaster lagi ka?
[10:01, 08/06/2024] EG MALL ECONMECH Dart: @Azman HKL @~Roxas Ng (Kai)

[10:02, 08/06/2024] Azman HKL: 7th floor. TB6. @EG MALL Mr Lo  please help to check and comment. Slab rebar not tally to archi drawing. Will affect the toilet room. Pic shows slab beam at the center.

[10:02, 08/06/2024] Azman HKL: Given archi drawing. Wall flush with column. We effect the toilet room and pipe sleeve.
[10:05, 08/06/2024] Azman HKL: @~nas4rie @~Roxas Ng (Kai) tolong check ini. Sebab itu hari kita pakai untuk itu cement pipe sleeve. Subcon GnB tiada orang. Mungkin kita pakai orang sendiri. Cc. @Mr. Voo
[10:07, 08/06/2024] Azman HKL: Riser kalau tiada pintu macam tidak tatai. Tolong saya confirm bos @~Roxas Ng (Kai) @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘”
[10:07, 08/06/2024] Azman HKL: Macam itu SPD riser
[10:08, 08/06/2024] EG MALL ECONMECH Dart: Klau xda sy psg duct ow

[10:09, 08/06/2024] Azman HKL: @EG MALL ECONMECH Dart client sama consultant. Mereka tunggu kamu punya request/inform maw shift ini pintu. πŸ™. Tolong atur cepat.

[10:12, 08/06/2024] EG MALL Mr Lo: nanti tu tandas part ada tambahan slab
[10:13, 08/06/2024] EG MALL ECONMECH Dart: Ya ni hari submit
[10:14, 08/06/2024] EG MALL Mr Lo: kami x tingkat 7 archi yang confirm punya
[10:16, 08/06/2024] Azman HKL: Jadi plumbing ikut itu archi sajala ya. πŸ‘Œ
[10:17, 08/06/2024] +60 12-559 6863: Lo, which part of the toilet need top up slab?

[10:18, 08/06/2024] EG MALL Mr Lo: To form up a toilet compartment
[10:18, 08/06/2024] +60 12-559 6863: which drawing shows
[10:18, 08/06/2024] +60 12-559 6863: ?
[10:18, 08/06/2024] EG MALL Mr Lo: Whg latest drawing 7th floor layout
[10:19, 08/06/2024] +60 12-559 6863: which date?
[10:19, 08/06/2024] +60 12-559 6863: we have casted the slab long time, still need top up?
PART OF 7TH FLOOR PLAN (L7-14 REV. 1) 05.06.2024.pdf
[10:19, 08/06/2024] +60 12-559 6863: using what to top up?
[10:19, 08/06/2024] +60 12-559 6863: any instructions?
[10:19, 08/06/2024] EG MALL Mr Lo: belum tuang
[10:19, 08/06/2024] +60 12-559 6863: TB/6?
[10:20, 08/06/2024] EG MALL Mr Lo: ya
[10:20, 08/06/2024] +60 12-559 6863: why can't we cast thicker instead of top up?
[10:20, 08/06/2024] EG MALL Mr Lo: that part will cast higher
[10:21, 08/06/2024] +60 12-559 6863: do it one time since the slab is not cast
[10:21, 08/06/2024] +60 12-559 6863: to avoid double handling
[10:21, 08/06/2024] EG MALL Mr Lo: noted
ini archi drawing received yesterday
[10:30, 08/06/2024] +60 12-559 6863: ok
[10:30, 08/06/2024] Mr. Voo: Yes , do later together with upper slab
[10:31, 08/06/2024] +60 12-559 6863: @Azman HKL itu pasal level tidak sama, jadi toilet kena cast kemudian pasal levelnya tinggi
[10:31, 08/06/2024] +60 16-832 2597: Saya tatai saja, lepas tu ko boleh pasang dah
[10:33, 08/06/2024] Azman HKL: Noted.
[10:34, 08/06/2024] EG MALL ECONMECH Dart: Fad riser suda tatai

[10:34, 08/06/2024] EG MALL ECONMECH Dart: Ea riser sdh tatai
[10:35, 08/06/2024] EG MALL ECONMECH Dart: @Azman HKL tlg man d atas L15 dan keatas ksi tatai dia sy mo jln duct
[10:35, 08/06/2024] EG MALL ECONMECH Dart: Material sdh smpai d site
[10:37, 08/06/2024] Azman HKL: Ok. @~Roxas Ng (Kai) kasi samala. Tolong kejar juga supaya ducting boleh jalan. Nanti tidak payah kerja dua kali. πŸ™
[10:39, 08/06/2024] +60 16-832 2597: Ok; dorg akan juga buat

[10:40, 08/06/2024] EG MALL ECONMECH Dart: L15

[10:40, 08/06/2024] EG MALL ECONMECH Dart: Pressurise jg @~Roxas Ng (Kai)
[10:41, 08/06/2024] +60 16-832 2597: Akan juga bossku; tadi sudah saya info org ko di site tadi 🀝
[10:42, 08/06/2024] EG MALL ECONMECH Dart: πŸ™πŸΌπŸ‘Œ

[11:51, 08/06/2024] EG MALL ECONMECH Dart: @Azman HKL kami suda buka sndri. πŸ˜…

[11:53, 08/06/2024] EG MALL ECONMECH Dart: @~Roxas Ng (Kai) plaster tatai ka ni kai? Tlg ksi plaster mo psg pressurise duct. St06
[11:54, 08/06/2024] +60 16-832 2597: Yea

[12:04, 08/06/2024] EG MALL ECONMECH Dart: @HIDAYA KH office Num hidayah jgn jln ngam2 opening sy
[13:20, 08/06/2024] Azman HKL: Tolong bicang diorang boss ksi lari dulu itu ducting... Kmi tidak mau buat tu klau adah ducting
[13:21, 08/06/2024] Azman HKL: @EG MALL ECONMECH Dart tolong ini ducting. Kami punya subcon tidak dapat plaster. Mereka minta kasi turun itu ducting.

[13:52, 08/06/2024] EG MALL ECONMECH Dart: Ni man kmi sdh buka joint tggl ksi sasar seja sikit
[13:52, 08/06/2024] EG MALL ECONMECH Dart: Ducting kmi sdh pnjg joint tu
[13:52, 08/06/2024] EG MALL ECONMECH Dart: Xble kmi buka2 gitu man. Ksi mnta tlg ksi sasar seja la
[14:01, 08/06/2024] Azman HKL: Subcon plaster tidak maw. Sudah bincang pun tidak maw. Mereka minta saya bincang sama kamu.

[14:16, 08/06/2024] +60 12-559 6863: Why still use this for working when red tag is on?

[14:21, 08/06/2024] +60 12-559 6863: Stop using @Jimmy HKL take action
[14:21, 08/06/2024] Jimmy HKL: noted bos
[14:23, 08/06/2024] Jimmy HKL: @HIDAYA KH office Num pastikan mana2 mobile scaffolding yg kamu mau gunapakai telah di perbaiki bgth saya untuk minta scaffolder dtg cek.

[14:27, 08/06/2024] +60 12-559 6863: Lubang ini apa?
[14:27, 08/06/2024] +60 12-559 6863: Ini pakai hacking bukan coring, sape allow hacking slab?
[14:37, 08/06/2024] +60 12-559 6863: Azman?
[14:40, 08/06/2024] HIDAYA KH office Num: noted boss
[14:45, 08/06/2024] Azman HKL: Who allowed? I'm not allowed. @~WY ducting opening kan? Ini itu hari saya tgk kamu coring. Tapi itu tepi shape dia square not circle. Kamu explain saya, kamu hack siring tapi pecah di bawah. Tolong explain balik.
[14:54, 08/06/2024] Azman HKL: @~ShawnChia kamu punya busduct ada sudah di site?
[14:59, 08/06/2024] +60 16-837 8881: Ya

[15:03, 08/06/2024] Azman HKL: Noted. We try to push electrical riser 13th floor to 8th floor by next week. Dalam meeting kita ada cakap. Tapi saya rasa mungkin akan ambil masa lagi. Plastering ongoing. Painting belum, dan screeding belum. @~Roxas Ng (Kai) tolong push ya. Inform @EG Mall Shafee nanti. πŸ™
[15:14, 08/06/2024] +60 16-837 8881: Tq πŸ‘πŸ»πŸ‘πŸ»


[15:46, 08/06/2024] Azman HKL: Cip tolong bagi tau mandur kayu dulu ba suru kasi bersi ni kita ada poin ba di tempat ni nanti tidak sempat lagi kita buat
[15:47, 08/06/2024] Azman HKL: @~nas4rie tolong dulu. Supaya boleh jalan kerja sini. πŸ™
[15:48, 08/06/2024] +60 10-941 8970: Ok noted
[15:48, 08/06/2024] Azman HKL: TQ nas. 🫰