Friday, June 7, 2024

7 JUN 2024 HKL

 SITE EG MALL

[08:39, 07/06/2024] +60 16-832 2597: 6F ST06 inspection for setting out (brick)

[09:12, 07/06/2024] +60 16-832 2597: 6F ST07 inspection for setting out (brick)
[09:16, 07/06/2024] Kadapi J. PROMES: Please be inform that, Boss Lan instructed me to inform all the party's to HOLD wiring work's for all HOTEL GUEST ROOM until gain final layout from ID. Tq and GOOD MORNINGπŸ™‚
[09:19, 07/06/2024] Azman HKL: Noted.
[09:21, 07/06/2024] Kadapi J. PROMES: Dear KH, i discussed with Boss Lan regarding this matter he ask u to cantact him or meet him to discuss this issue. Please do it early other wise it will be too late and become a big problem. Tq

[09:24, 07/06/2024] +60 16-832 2597: 6F ST05 inspection for setting out (brick)

[10:44, 07/06/2024] Azman HKL: 15th floor. HR room. Can we propose to shift the HR room 400mm due to as built in site? @⁨EG Mall Archie Johnny⁩ @⁨Kadapi J. EG Mall Promess Gadapi⁩ later we discuss if only possible πŸ™.

[10:44, 07/06/2024] Azman HKL: KH flow trap and econmech riser pipe opening to avoid slab coring. Green line as per drawing. Red line proposal.
[10:49, 07/06/2024] Kadapi J. PROMES: To shifting riser nor wall have to discuss with RA. I have no right to make a disision. Anyway we will discuss this asap.



[14:20, 07/06/2024] +60 16-832 2597: 10F Tower A unit 11-13 brick wall level pegs inspection

NSC GROUP

[08:41, 07/06/2024] Azman HKL: Site progress photo.
7/6/24.
21st floor. TA.

[08:41, 07/06/2024] Azman HKL: 7th floor. TB6. Slab rebar and M&E in progress.

[08:41, 07/06/2024] Azman HKL: 3rd floor. Z8. Slab formwork and beam rebar in progress

[08:41, 07/06/2024] Azman HKL: External ground floor. HDPE PN10 pipe earth excavation in progress

[09:15, 07/06/2024] Azman HKL: 2nd floor. Electrical riser. @~Roxas Ng (Kai) ada 3 org buat riser di 2nd floor sahaja dan mungkin 2minggu untuk siap 1 floor. Progress kita slow. Maw kasi speed lagi. Tolong dulu ok ush lagi kita punya subcon. πŸ™. Bos @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” tolong dulu advise. πŸ™
[09:16, 07/06/2024] Azman HKL: @~LO KEAM @~Leppong hari ini kamu punya Busduct sampai site kan?
[09:17, 07/06/2024] +60 16-832 2597: Ok; saya kasih tlg push dia lagi
[09:17, 07/06/2024] Azman HKL: TQ @~Roxas Ng (Kai) πŸ™πŸ™

[09:24, 07/06/2024] Azman HKL: Lift shaft, hotel, ground floor - 13th floor @Jimmy HKL for safety work inside lift shaft. Kami maw request maw pasang plywood macam begini di setiap pintu lift. Boleh nanti kita bincang detail dia? Kalau boleh minggu depan siap. πŸ™
[09:25, 07/06/2024] +60 12-559 6863: @Jimmy HKL atur pasang supaya lift bolih jalan

[09:33, 07/06/2024] Azman HKL: 8th floor. Electrical riser. Wall plastering in progress.
[09:33, 07/06/2024] Jimmy HKL: Boleh bah nanti di cek dulu mana2 pintu lift yg tiada plywood.
[09:36, 07/06/2024] Azman HKL: TQ Jim. Saya sini TA 9th Hotel kalau maw discuss inform saja.πŸ™

[09:37, 07/06/2024] Azman HKL: 9th floor. Electrical riser. @EG Mall Shafee ini sebelah maw plaster juga ka? Nanti tolong jak cek kasi confirm. Alang2 kena buat.
[09:39, 07/06/2024] Jimmy HKL: orite man πŸ’ͺ🏻πŸ’ͺ🏻πŸ’ͺπŸ»πŸ‘πŸ»

[09:41, 07/06/2024] Azman HKL: 10th floor. TA. Electrical riser. Plaster

[09:43, 07/06/2024] Azman HKL: Zone TA/2: 18F-19F: ST05a: Fmwk belum siap @+60 19-530 2811 @+60 17-238 9414 atur orng buat, @Azman HKL tlg bubut electrical buat tu conduit ni hari mau cast πŸ™πŸ™πŸ™
[09:43, 07/06/2024] Azman HKL: @~Leppong tolong pg cek sana. πŸ™

[09:45, 07/06/2024] Azman HKL: 11th floor. @~WY jangan kasi mati terus kalau pasang ducting sini ya. Biar jalan dulu plaster. Nanti saya push tukang plaster. πŸ™kamu kejar saya kalau urgent.
[09:46, 07/06/2024] +60 14-379 2990: Noted.

[09:47, 07/06/2024] Azman HKL: 11th floor. Electrical riser. Wall plaster.

[09:49, 07/06/2024] Azman HKL: 12th floor. Electrical riser. Wall brick laying and plaster in progress

[09:56, 07/06/2024] Azman HKL: 13th floor.

[09:56, 07/06/2024] Azman HKL: 14th floor.
[10:00, 07/06/2024] Azman HKL: Electrical riser urgent. 7th floor to 13th floor to complete. So Busduct for the Hotel can proceed. @~Roxas Ng (Kai) @EG Mall Shafee πŸ™

[10:17, 07/06/2024] Azman HKL: 15th floor. @~WY kamu sudah cek bah kan itu wall opening. Boleh masuk duct juga.

[10:17, 07/06/2024] Azman HKL: 15th floor. FAD & EAD riser room. @~WY @~Rimon Joseph Ini juga. Ada lari sikit. Tolong saya cek kali2 ya.

[10:19, 07/06/2024] Azman HKL: Ini bata sama beam opening macam lari..tolong cek kali2, kamu boleh pasang atau tidak.


[10:20, 07/06/2024] Azman HKL: Ini tidak lurus..
[10:36, 07/06/2024] EG Mall Shafee: Ok
[11:10, 07/06/2024] +60 14-379 2990: @Azman HKL @~Roxas Ng (Kai)  str 6 brick wall belum hack.. kami tidak dapat pasang ducting?
[14:21, 07/06/2024] Azman HKL: @Azman HKL kasi confirm ko punya m&e…next week saya suruh jalan plaster level 10…
[14:22, 07/06/2024] Azman HKL: Pls take note. @HIDAYA KH office Num @~zee @~Leppong πŸ™

[14:26, 07/06/2024] Azman HKL: HDPE PN10 works in progress.

[15:30, 07/06/2024] Azman HKL: 11th floor. Joint Inspection floor level.

[16:31, 07/06/2024] Azman HKL: Pre inspection with consultant. HDPE PN10
[17:18, 07/06/2024] Azman HKL: @King Hong Office @~Frankie Yee please check  if any
[17:19, 07/06/2024] +60 17-866 9697: Will do