SITE EG MALL
[09:49, 04/06/2024] Azman HKL: 7th floor. TB4. M&E slab inspection in progress.
[10:51, 04/06/2024] Azman HKL: Plinth inspection 21st floor.
[14:13, 04/06/2024] +60 16-832 2597: ST05 GF-1F nosing inspection
NSC GROUP
[10:13, 04/06/2024] Azman HKL: Site progress photo.
4/6/24.
21st floor. Plinth in progress.
[10:13, 04/06/2024] Azman HKL: 3rd floor. Z8. Slab formwork in progress
[10:13, 04/06/2024] Azman HKL: 7th floor. TB4. M&E services inspection in progress
[10:15, 04/06/2024] Azman HKL: 6th floor. Z8. Slab formwork in progress
[10:23, 04/06/2024] Azman HKL: 7th floor. TB4. M&E inspection in progress
[10:39, 04/06/2024] Azman HKL: 21st floor. Plinth inspection.
[10:51, 04/06/2024] Azman HKL: Plinth inspection 21st floor.
[13:33, 04/06/2024] Azman HKL: 8th floor. @EG Mall Shafee ini macam mana? Maw plaster sampai atas lagi ka?
[13:34, 04/06/2024] Azman HKL: @~Rimon Joseph tolong cek ini. Itu ducting level siling.
[13:37, 04/06/2024] Azman HKL: 8th floor. 20&21 Riser room sample unit. Sudah paint. @HIDAYA KH office Num @~Rimon Joseph tolong atur ya. Sample unit kita. 🙏
[13:37, 04/06/2024] Azman HKL: 8th floor. Sample unit 22.
[13:41, 04/06/2024] +60 12-559 6863: Mesti
[13:45, 04/06/2024] Azman HKL: @~Rimon Joseph @~WY tolong bincang sama kamu punya subcon. Untuk bagi ruang supaya plaster dapat jalan di situ.
[13:49, 04/06/2024] EG Mall Shafee: Dlm contract plaster full bro…
[13:53, 04/06/2024] Azman HKL: Okay bro. Kejar semua plaster wall. Jangan tangguh2 lagi. Buka pasang buang banyak masa. Lama kita kejar ini plaster skrg baru jalan.
[13:58, 04/06/2024] EG Mall Shafee: Orite