Thursday, June 13, 2024

14 JUN 2024 HKL

SITE EG MALL

[08:20, 14/06/2024] Azman HKL: Good morning.
1. 8th floor. Request to continue joint inspection electrical & ELV services at the brick wall. Unit 1-10, 11-13,  9am.
@~sam @Kadapi J. PROMES . DCC @~s4yamahuk4ya88.gmail.com  and LSK @~zee please standby during inspection. 🙏
[08:23, 14/06/2024] +60 16-837 8881: Morning
Kita inspect guna drawing apa ?
[08:27, 14/06/2024] +60 19-895 9900: Utk abortive work

[09:16, 14/06/2024] Edwin Chen 013: @~Roxas Ng (Kai), the shower mixer should be here?

[09:16, 14/06/2024] Edwin Chen 013: Room 1. Level 8
[09:16, 14/06/2024] +60 12-559 6863: Edwin, Shaffee is the PIC for Tower A now
[09:17, 14/06/2024] +60 12-559 6863: @EG Mall Shafee
[09:17, 14/06/2024] EG Mall Shafee: Saya ada sini level 8
[09:19, 14/06/2024] Edwin Chen 013: Can meet at room 1?
[09:19, 14/06/2024] EG Mall Shafee: Level 9 la u bkn level 8
[10:37, 14/06/2024] Azman HKL: 8th floor. Continue joint inspection for Electrical and ELV socket/switches at Hotel Wall. Unit 11.

[10:37, 14/06/2024] Azman HKL: Unit 10.

[10:40, 14/06/2024] Azman HKL: U9

[10:40, 14/06/2024] Azman HKL: U8

[10:41, 14/06/2024] Azman HKL: u7

[10:41, 14/06/2024] Azman HKL: U5

[10:41, 14/06/2024] EG Mall Shafee: Level 15…tengahri diorang buka formwork @Azman HKL @~WY
[10:43, 14/06/2024] +60 14-379 2990: Thank you ya.. 🙏🏻🙏🏻

[10:55, 14/06/2024] Azman HKL: U4.

[10:56, 14/06/2024] Azman HKL: U3

[10:56, 14/06/2024] Azman HKL: U2

[10:56, 14/06/2024] Azman HKL: U1

[10:57, 14/06/2024] Azman HKL: U23

[10:58, 14/06/2024] Azman HKL: U24

[11:45, 14/06/2024] Edwin Chen 013: Same issue at Room 10. Please check
[11:46, 14/06/2024] Edwin Chen 013: @EG Mall Shafee
[12:04, 14/06/2024] EG Mall Shafee: Ok…



NSC GROUP

[09:51, 14/06/2024] Azman HKL: Site photo progress.
14/6/24.
21st floor. Tower A
[10:32, 14/06/2024] Azman HKL: 3rd floor. Z8. Slab cast.

[10:33, 14/06/2024] Azman HKL: 7th floor. TB 6. Slab rebar and formwork.

[10:33, 14/06/2024] Azman HKL: 7th floor. Column rebar and beam works in progress.

[11:30, 14/06/2024] Azman HKL: External ground floor. Drainage work in progress. @HIDAYA KH office Num tolong cek nanti ya itu paip yang turun ke drainage. 🙏
Econmech please take note
[14:32, 14/06/2024] EG MALL ECONMECH Dart: Thanks Mr Raymond 🙏🏼

[14:42, 14/06/2024] Azman HKL: 8th floor. Continue joint inspection for Electrical and ELV socket/switches at Hotel Wall. Unit 11.

[14:42, 14/06/2024] Azman HKL: U4.

[14:43, 14/06/2024] Azman HKL: U24
 