Monday, June 10, 2024

11 JUN 2024 HKL

 SITE EG MALL


[09:56, 11/06/2024] +60 16-880 4632: @EG Mall Shafee please check dimension
[10:00, 11/06/2024] EG Mall Shafee: Ok boss…

[11:05, 11/06/2024] +60 12-559 6863: @~Johnny this is due to drawing changed, will add brick wall there



[14:22, 11/06/2024] +60 16-832 2597: Tower A 15F toilet setting out inspection

[14:54, 11/06/2024] Azman HKL: External HDPE PN10. Inspection with a consultant.
[14:56, 11/06/2024] +60 12-559 6863: ada pasir atas itu HDPE pipe bila backfill nanti


[15:25, 11/06/2024] Kadapi J. PROMES: 1: Please check with surveyor if the pipe sleeve clash with the piling.
2: due to pipe sleeve under the road, please attach with MOS either using sand back filling or encast.
3: Please prepare approved shop drawing due to actual installation diffrent with construction drawing the number of pipe sleeve.
4: Please check with CnS and surveyor coz the rc road too thick.
[15:28, 11/06/2024] Kadapi J. PROMES: @Azman HKL ,@~Leppong ,@~s4yamahuk4ya88.gmail.com. Please take note.👆👆👆
[15:29, 11/06/2024] +60 12-559 6863: Just checked with Lawrence, since this will be RC road so sand filling is mot required


[15:55, 11/06/2024] +60 12-559 6863: Why need stiffener there?
[15:56, 11/06/2024] +60 12-559 6863: Just 3.5M height
[16:05, 11/06/2024] Kadapi J. PROMES: My addvice it is good idea if the pipe sleeve install after retaining wall done coz during retaining wall excavation it may damage or disalignment the pipe sleeve. Tq
[16:07, 11/06/2024] Azman HKL: Noted.


NSC GROUP

[08:23, 11/06/2024] Azman HKL: Site progress photo.
11/6/24
21st floor. TA.

[08:23, 11/06/2024] Azman HKL: 7th floor. TB6. Slab cast.

[08:23, 11/06/2024] Azman HKL: Ramp 4. Slab rebar in progress.
Z8. Formwork and beam rebar in progress.

[08:23, 11/06/2024] Azman HKL: 7th floor. Column works in progress.

[09:13, 11/06/2024] Azman HKL: External HDPE PN10 pipe excavation and laying pipe in progress.
[09:48, 11/06/2024] Azman HKL: @~Leppong tolong kasi confirm itu semua Consultant komen on site. 🙏. Kita maw cepat siap ini tempat supaya lain subcon boleh masuk kerja.

[10:21, 11/06/2024] Azman HKL: 3rd floor. @~WY tolong cek in pipe sleeve. Tutup tu lubang cepat sebelum ada lain masalah. 🙏

[10:41, 11/06/2024] Azman HKL: Mitsubishi team erecting scaffolding at lift shaft Hotel. 👆

[11:12, 11/06/2024] Azman HKL: Material inspection. Temporary storage at ground floor

[13:36, 11/06/2024] Azman HKL: Just received, today the Coordination meeting postponed. 🙏
[13:37, 11/06/2024] +60 16-837 8881: 👌🏻

[14:43, 11/06/2024] Azman HKL: @Azman HKL  lvl 13 room 1  pipe sprinkler …duduk atas bata saya….
[14:44, 11/06/2024] Azman HKL: @~WY bro. Tolong  Cek sana dulu. Itu pipe sprinkler. 🙏🙏

[14:46, 11/06/2024] +60 14-379 2990: Okay man.

[14:49, 11/06/2024] Azman HKL: Memang tiada pakai grinder dulu…@Azman HKL  ni KH…
[14:49, 11/06/2024] Azman HKL: @HIDAYA KH office Num tolong minta potong brick guna grinder dulu. 🙏

[14:51, 11/06/2024] HIDAYA KH office Num: sepatutnya mmg kami guna grinder dulu tu. nanti saya pegi check
[15:42, 11/06/2024] +60 12-559 6863: Dear all NSCs, let’s have a site walk at 8F and 9F tomorrow morning 9am
[15:42, 11/06/2024] +60 12-559 6863: Just for site coordination matters
[15:42, 11/06/2024] +60 12-559 6863: @Azman HKL please arrange

[15:53, 11/06/2024] Jimmy HKL: @Azman HKL start buat protection lif guna plywood.
[17:00, 11/06/2024] Azman HKL: Noted. @~Leppong @~WY @~zee @HIDAYA KH office Num please join us tomorrow. Site walk, 8F and 9F.