Tuesday, May 7, 2024

8 MAY 2024 HKL

SITE EG MALL
[12:15, 08/05/2024] EG MALL ECONMECH Dart: Already inspect and stdy this case. Coordination dwg supposed to achieve 2400 ceiling height where our bottom of duct hv space around 100mm. But site condition cant achieve as per coordination dwg. As i measure roughly its only 2930-2950 (soffit to slab). On coordination dwg is 3050 (soffit to slab). @Kadapi J. PROMES for you info. @Azman HKL pls stdy πŸ™πŸΌ
[12:20, 08/05/2024] Azman HKL: Noted. On site, the bracket bottom height maximum was 2380mm for the 8th floor corridor.





[15:06, 08/05/2024] +60 16-832 2597: 14F toilet inspection setting out
[15:06, 08/05/2024] Azman HKL: 13th -8th floor. Inspection SD point wiring with consultant.

[15:14, 08/05/2024] Azman HKL: 11th floor. Exposed conduit at lift lobby. @~s4yamahuk4ya88.gmail.com @~Leppong . Consultant comment to rectify using correct material. πŸ™

[15:14, 08/05/2024] Azman HKL: Please rectify as per consultant comment. πŸ‘†
[16:38, 08/05/2024] +60 17-866 0355: Ok man

NSC GROUP

[09:49, 08/05/2024] Azman HKL: Site progress photo.
8/5/24.
21st floor. Tower A. Slab tebar and M&E in progress.

[09:49, 08/05/2024] Azman HKL: 6th floor. TB6. Slab cast. 7th floor. TB5. Slab formwork and rebar in progress.

[09:49, 08/05/2024] Azman HKL: 7th floor. TB5. Slab formwork, rebar and M&E in progress.

[09:49, 08/05/2024] Azman HKL: 3rd floor. Z8. Slab formwork and rebar in progress.
[10:05, 08/05/2024] Mr. Voo: Laju jg ko pg 3rd flr sdh man
[10:12, 08/05/2024] Azman HKL: 2nd floor. 🫣

[10:59, 08/05/2024] Azman HKL: 10th floor. @~Leppong @~s4yamahuk4ya88.gmail.com please make good as per consultant comment. Subcon will start wall plastering. πŸ‘†πŸ™.
[11:03, 08/05/2024] +60 12-559 6863: Azman, what comment and by who?
[11:04, 08/05/2024] +60 12-559 6863: DCC just proceed with your hacking and installation works, should any one telling u to stop please ask them for written instruction
[11:05, 08/05/2024] +60 17-866 0355: @Azman HKL  sedang buat bos
[11:06, 08/05/2024] Mr. Voo: @~Roxas Ng (Kai)  @Edwin Chen 013  fyi also
[11:06, 08/05/2024] Mr. Voo: Ni
[11:09, 08/05/2024] Azman HKL: Comment to make good. Not  to stop work la bos. So Plastering can start. Already discussed with DCC, they will do rectification on site.
[11:09, 08/05/2024] +60 12-559 6863: Oh ok if like that

[11:19, 08/05/2024] Azman HKL: @HIDAYA KH office Num tolong cek ini. Kamu punya pipe boleh jalan bawah tu sprinkler ka?
[11:20, 08/05/2024] HIDAYA KH office Num: okay2 nnt cek
[11:24, 08/05/2024] Azman HKL: Sorry ini 13th floor. Kamu punya 14th. πŸ™ini @~WY punya lubang.

[12:15, 08/05/2024] Azman HKL: Site coordination at 8th floor. Hotel with Econmech
[12:27, 08/05/2024] Edwin Chen 013: Means I can proceed with the hacking and cutting the bricks without plastering? Correct me if I am wrong
[12:35, 08/05/2024] Mr. Voo: @~Roxas Ng (Kai) @Azman HKL  anyone hold his work ?what reason ?
[12:36, 08/05/2024] +60 16-832 2597: No one hold, RA only concern about the bricks bonding issues only..
[12:39, 08/05/2024] Mr. Voo: Then plz proceed
[12:40, 08/05/2024] Edwin Chen 013: Go go go
[12:41, 08/05/2024] Mr. Voo: But make sure u have the final drawing ya πŸ˜…
[12:52, 08/05/2024] Azman HKL: No hold.
[14:25, 08/05/2024] Azman HKL: Pipe ke MH4 & MH6. @HIDAYA KH office Num nanti kalau siap sudah kita panggil konsultan pg cek sana. Dpt ni hari ka?
[14:28, 08/05/2024] HIDAYA KH office Num: esok\

[14:59, 08/05/2024] Azman HKL: 13th -8th floor. Inspection SD point wiring with consultant.




[15:18, 08/05/2024] Azman HKL: 10th floor. Wall conduit Rectification work.

[15:18, 08/05/2024] Azman HKL: 10th floor. Conduit rectification work in progress.
[15:41, 08/05/2024] EG MALL ECONMECH Dart: @Azman HKL @EG MALL Mr Lo Submit today
[15:43, 08/05/2024] EG MALL Mr Lo: Plinth ubah lain Dari Archi punya kah
[15:45, 08/05/2024] EG MALL ECONMECH Dart: ya ikut scupper
[15:59, 08/05/2024] Azman HKL: @HIDAYA KH office Num kamu punya plinth ngam sudah ka tu?
[16:20, 08/05/2024] HIDAYA KH office Num: KH punya nanti akan submit dengan promes juga. tunggu comment dari consultant nanti
[16:26, 08/05/2024] Azman HKL: Ok.

[16:28, 08/05/2024] EG MALL Mr Lo: @EG MALL ECONMECH Dart
[16:29, 08/05/2024] EG MALL Mr Lo: mana dapat