[09:02, 22/05/2024] Azman HKL: Morning.
To all NSCs. For info, 8th floor (transfer plate) there are prestressed slab of 1150mm thk grade 45. Please double check the M&Es service drawing. If any need services slab opening please inform HKL. @~LO KEAM @EG MALL ECONMECH Dart @HIDAYA KH office Num @~At Work @~YoonYK
[09:06, 22/05/2024] EG MALL ECONMECH Dart: Ok noted man 🙏🏼
[09:07, 22/05/2024] Azman HKL: CAD drawing.

[09:10, 22/05/2024] Azman HKL: Site progress photo. 
22/5/24.
21st floor. TA. Slab cast.

[09:10, 22/05/2024] Azman HKL: 7th floor. TB5. Slab rebar and M&E.

[09:10, 22/05/2024] Azman HKL: 7th floor. TB6. Beam formwork and rebar in progress.

[09:10, 22/05/2024] Azman HKL: 7th floor. TB4. Slab formwork and beam rebar in progress.

[09:10, 22/05/2024] Azman HKL: External MH12 excavation in progress

[09:13, 22/05/2024] Azman HKL: External MH1. Outlet pipe MH1 in progress.

[09:13, 22/05/2024] Azman HKL: External MH2. Outlet pipe connection to MH2 in progress.

[09:49, 22/05/2024] Azman HKL: 6th floor. Column done skim. @HIDAYA KH office Num 👆

[14:44, 22/05/2024] Azman HKL: External MH 13. mH and pipe excavation in progress.