[10:17, 02/05/2024] +60 16-880 4632: Level 8 No activities carry out since last Thursday.

[10:26, 02/05/2024] +60 16-880 4632: Level9.Arch work NO Activities




[10:51, 02/05/2024] +60 16-880 4632: L10 & L11 Brick laying works door frame installation progress on going..





[11:08, 02/05/2024] +60 16-880 4632: L14 RC beam Honeycomb to rectify and make good.



[11:14, 02/05/2024] +60 16-880 4632: L14 Brickworks progress on going..


 NSC GROUP 

[09:19, 02/05/2024] Azman HKL: Site progress photo.
5/2/24
21th floor. TA1, slab support and beam formwork in progress. TA2. Column and lift rebar in progress

[09:19, 02/05/2024] Azman HKL: 6th floor. TB4. Slab form work and rebar in progress. 6th floor. TB5 beam rebar and slab rebar in progres

[09:19, 02/05/2024] Azman HKL: 7th floor. Slab rebar in progress

[09:19, 02/05/2024] Azman HKL: 6th floor. Slab formwork in progress.
[09:22, 02/05/2024] HIDAYA KH office Num: @Azman HKL sini ada access untuk naik ka?

[14:29, 02/05/2024] Azman HKL: As per the last M&E Coordination meeting discussion. Outstanding item on site to solve.
1. 8th floor. A sample layouts routing as per request from clients especially ducting.
2. DCC requests to HKL expedite all Electrical/Tel/Elv riser room for office and Hotel.
3. KH informs that some of the sprinkler room wall without plaster. HKL has to do.
4. Mitsubishi cant start work due to safety issues at the Office/Hotel lift shaft.
5. 8th floor sample unit, brickwall no progress due to lift wall not complete. 
6. 21st floor. All NSC should inform any opening and plinth ASAP to HKL.

[14:31, 02/05/2024] Azman HKL: 11th floor. Brickwall in progress.

[14:34, 02/05/2024] Azman HKL: 7th floor. TB5. Slab rebar and M&E in progress.

[14:34, 02/05/2024] Azman HKL: 6th floor. TB4. Slab rebar in progress.

[14:34, 02/05/2024] Azman HKL: 6th floor. TB6. Slab formwork in progress.
[14:54, 02/05/2024] Azman HKL: The site meeting will start soon