[09:29, 17/05/2024] +60 16-832 2597: Inspection setting out at 15F
[09:29, 17/05/2024] Jimmy HKL: noted bos

[14:38, 17/05/2024] Azman HKL: 8th floor. Tower A. We request site walk and discussion of 
1. M&E services layout 
2. Ceiling height 
at 9am with the Consultant. @Kadapi J. PROMES @~Johnny please to join. NSC @EG MALL ECONMECH Dart @~Leppong @~ShawnChia @~LO KEAM @Edwin Chen 013 @HIDAYA KH office Num @~At Work @~zee
[15:21, 17/05/2024] Kadapi J. PROMES: Bila ni? Hari?
[15:22, 17/05/2024] Kadapi J. PROMES: Monday?
[15:25, 17/05/2024] Azman HKL: Saturday tomorrow..
[15:29, 17/05/2024] Azman HKL: Boleh bsok @Kadapi J. PROMES kalau tidak dapat, monday 9.30am la.
[15:30, 17/05/2024] Kadapi J. PROMES: Ok Monday
[15:31, 17/05/2024] Kadapi J. PROMES: Esok aku cuti ada hal.
[15:34, 17/05/2024] Azman HKL: Site walk.
Monday. 9.30am. πŸ™
[15:34, 17/05/2024] EG MALL ECONMECH Dart: Affirmative πŸ™πŸΌ


NSC GROUP

[08:29, 17/05/2024] Azman HKL: Site progress photo.
17/5/24
21st floor. TA1. Slab rebar and M&E in progress.

[08:29, 17/05/2024] Azman HKL: 6th floor. TB4. Beam forwork in progress. TB6. Lift wall formwork and ST2 RC wall rebar in progress.
7th floor. TB5. Slab cast.

[08:39, 17/05/2024] Azman HKL: 3rd floor. Cold water pump room. @~WY @EG MALL ECONMECH Dart itu expansion tank sudah confirm ka? Pastikan boleh masuk ikut itu pintu ya. Tgk lebar sama tinggi pintu. Plinth itu cek kompom dia. On site tidak sama sda tu.

[08:41, 17/05/2024] Azman HKL: @HIDAYA KH office Num itu equipment kamu kasi masuk didalam sini la. Siap sda tu lantai. Subcon maw pasang pintu sda.

[08:56, 17/05/2024] Azman HKL: External MH1 dan MH2 in progress.
[09:04, 17/05/2024] EG MALL ECONMECH Dart: Non officially dscuss. Cinema mcm mo guna chiller from basement to L7, so expansion must be top / above all my chiller pipe. Tba la man. πŸ™πŸΌ kemungkinan expansion tank akan d L7 πŸ™πŸΌ

[09:07, 17/05/2024] EG MALL Mr Lo: @EG MALL ECONMECH Dart mesti macam ni sudah
[09:08, 17/05/2024] EG MALL Mr Lo: saya x mahu buka kayu atau tambah besi kecuali trimmer bar saja
[09:09, 17/05/2024] EG MALL ECONMECH Dart: Sy tggu promes confirm dlu πŸ™πŸΌ sy  ok saja jnji bole pasang. Tggu designer / consultant confirm πŸ™πŸΌ
[09:11, 17/05/2024] EG MALL ECONMECH Dart: Promes ok blang πŸ™πŸΌ
[09:11, 17/05/2024] EG MALL Mr Lo: ok
[09:12, 17/05/2024] Azman HKL: Tunggu official saja.

[09:13, 17/05/2024] Azman HKL: 9th floor. TA. Brickwall in progress.

[09:27, 17/05/2024] Azman HKL: 13 floor. @HIDAYA KH office Num kompom ya sudah cek dia boleh jalan tu pipe. Tolong liaise sama @~WY .

[09:39, 17/05/2024] Azman HKL: @HIDAYA KH office Num @Edwin Chen 013 please push to complete all this pipe connection to MH ASAP. Kita maw tutup semua lubang external cepat2 supaya parit boleh mula. πŸ™πŸ™


[10:07, 17/05/2024] Azman HKL: 15th floor @~YoonYK next week minta tolong kasi pindah ini barang. tekena itu brickwall. Sangat berat maw pindah. Subcon kami takut rosak

[10:38, 17/05/2024] Azman HKL: 21st floor. Lift motor room. @~YoonYK boleh datang untuk buat setting out openingπŸ‘†πŸ™

[10:48, 17/05/2024] Azman HKL: 21st floor. M&E in progress.
 
[14:08, 17/05/2024] Azman HKL: 8th floor. VRF pipe. @EG MALL ECONMECH Dart ini pipe VRF macamana? Lan sudah confirm? Skrg on site, sprinkler sama Plumbing minta inspection. Kalau ini VRF pipe dan ducting confirm baru itu lain2 servis ok. Kalau tidak, semua belum boleh proceed tu.
[14:10, 17/05/2024] Azman HKL: Atau kita panggil Chris naik check? Kalau reject semua maw buka balik.
[14:12, 17/05/2024] Azman HKL: Ini saya rasa, Kadapi pun akan minta kamu confirm sama Lan dulu. Sebab Lan ada inform minta pindah.
[14:14, 17/05/2024] EG MALL ECONMECH Dart: Kemarin dorg mau ceiling achieve 2.4m
[14:14, 17/05/2024] EG MALL ECONMECH Dart: Kta mau usahakan spya dpt ceiling 2.4m
[14:14, 17/05/2024] +60 12-559 6863: Dear all, refer to yesterday's site meeting, 8th floor hotel room No 20 & 22 will be site mock up units, kindly do whatever necessary
[14:15, 17/05/2024] Azman HKL: Ceiling level, kami sudah discuss on site, DCC dan Econmech boleh ejas untuk dapat 2.4m cuma skrg itu layout.
[14:15, 17/05/2024] EG MALL ECONMECH Dart: Kta pggl inspection la man sma client
[14:15, 17/05/2024] EG MALL ECONMECH Dart: Aku join skali
[14:16, 17/05/2024] EG MALL ECONMECH Dart: Dia ok sdh pndh x pindah. Dia hny mau ceiling 2.4m seja
[14:19, 17/05/2024] Azman HKL: 2.4m @~WY @~ShawnChia cuba adjust untuk dapat itu 2.4m seperti kita bincang dalam site coordination meeting. Untuk 8th floor. Baru panggil client. Kalau boleh next monday.
[14:22, 17/05/2024] Azman HKL: Kita adjust dulu on site dapat itu 2.4 ceiling height. Priority dulu ini level di 8th floor @~ShawnChia @~WY @~Leppong @HIDAYA KH office Num @~zee
[14:23, 17/05/2024] +60 16-837 8881: Saya apa mahu adjust ?
Tiada kan
[14:24, 17/05/2024] EG MALL ECONMECH Dart: Trunking ko ada mo ubah skit
[14:24, 17/05/2024] EG MALL ECONMECH Dart: Kta site walk esok bole?
[14:25, 17/05/2024] Azman HKL: Econmech minta adjusts sikit trunking.
[14:25, 17/05/2024] Azman HKL: Bsok kita site walk. 9AM. Kita bawa Kadapi sama Johny.
[14:26, 17/05/2024] EG MALL ECONMECH Dart: Sama2 tlg ya bro. Kalau pindah duct pergi dekat pintu guest room. Smua services piping mati sdh tu
[14:27, 17/05/2024] +60 16-837 8881: Apa macam mahu adjust trunking saya ?
Tu size fix sudah untuk cable
[14:27, 17/05/2024] Azman HKL: Bsok ya. Jam 9am. Kita discuss di site.
[14:43, 17/05/2024] EG MALL ECONMECH Dart: 9.30am bole? πŸ™πŸΌ
[14:58, 17/05/2024] +60 18-960 2589: Ok mam,
[15:28, 17/05/2024] Azman HKL: Nanti kompom di Coordination group ya.
[15:35, 17/05/2024] +60 18-960 2589: Man*