Thursday, May 16, 2024

16 MAY 2024 HKL

SITE EG MALL

[10:31, 16/05/2024] +60 16-880 4632: @EG MALL Mr Lo please check.
[10:31, 16/05/2024] EG MALL Mr Lo: ok


[10:45, 16/05/2024] +60 16-880 4632: @Jimmy HKL 
Another hazard on floor. Protruding rebar to remove..


NSC GROUP

[08:01, 16/05/2024] Azman HKL: Good morning.
Site progress photo.
16/5/24.
21st floor. TA. Slab rebar and M&E in progress.

[08:04, 16/05/2024] Azman HKL: 7th floor. TB5. Slab rebar and M&E. 6th floor. TB6 Lift wall formwork and rebar in progress

[10:23, 16/05/2024] Azman HKL: 6th floor. TB6. Lift wall formwork, and ST rebar in progress.

[10:23, 16/05/2024] Azman HKL: MH1 and MH2. Earth backfill in progress
[10:33, 16/05/2024] EG MALL Mr Lo: @EG MALL ECONMECH Dart boss tu loading saya minta tu ada ka
[10:58, 16/05/2024] EG MALL ECONMECH Dart: Passed
[11:00, 16/05/2024] EG MALL Mr Lo: 👍

[11:14, 16/05/2024] Azman HKL: MH19 outlet pipe connection in progress.
[13:19, 16/05/2024] Azman HKL: Today site meeting with client at site meeting room. Standby at 2.30pm. will start after consultant meeting.
[13:42, 16/05/2024] Azman HKL: New info. Meeting postponed to 4pm..

[14:15, 16/05/2024] Azman HKL: 21st floor. TA1. Slab rebar, M&E and formwork in progress.