SITE EG MALL


[09:26, 14/05/2024] +60 16-880 4632: Drawing height 1150.

[09:35, 14/05/2024] Mr. Voo: After finishing will be more and less
[09:40, 14/05/2024] +60 12-559 6863: Johnny, u forgotten tiles finish there?

[09:51, 14/05/2024] Azman HKL: 2nd floor. Z8. Request for M&E inspection at 10.00pm. @Kadapi J. PROMES . Site PIC please standby at site during inspection.

[09:52, 14/05/2024] Kadapi J. PROMES: I am here now. Come for ots inspection b 4 rain.
[10:00, 14/05/2024] Azman HKL: 🙏otw

[10:03, 14/05/2024] Azman HKL: 2nd floor, M&E inspection in progress.

[14:31, 14/05/2024] Azman HKL: Inspection done. @Mr. Voo @~nas4rie please proceed.


 NSC GROUP

[08:31, 14/05/2024] Azman HKL: Site progress photo.
14/5/24.
21st floor. TA. Slab formwork, rebar and M&E in progress

[08:31, 14/05/2024] Azman HKL: 6th floor. TB4. Column rebar , TB6 ST RC wall rebar and lift wall rebar in progress. 7th floor. TB5. Slab formwork, M&E and rebar in progress

[08:31, 14/05/2024] Azman HKL: 2nd floor. Z8. Slab rebar and M&E in progress.
[09:44, 14/05/2024] Azman HKL: Lower roof and Upper roof plan for Tower A.
[09:51, 14/05/2024] EG MALL ECONMECH Dart: Dwg lama ni man
[09:59, 14/05/2024] Azman HKL: Ada ya g baru ka? Ini yg kami terima. Nanti saya double check.
[09:59, 14/05/2024] Azman HKL: Kamu punya drawing slalu advance dari saya. 😩
[10:04, 14/05/2024] EG MALL ECONMECH Dart: jgn kasi orang lain2 ref kita2 saja
[10:11, 14/05/2024] Azman HKL: Ko sudah share sini.. 😅👆

[10:29, 14/05/2024] Azman HKL: MH1 . KH please put on the opening at the MH wall before closure.

[10:29, 14/05/2024] Azman HKL: MH19. Please connect the pipe to the MH. Liase with the external subcon on the site.
[12:52, 14/05/2024] HIDAYA KH office Num: okay azman
[13:49, 14/05/2024] Azman HKL: Site Coordination Meeting. 3.30pm after subcon Meeting. Site meeting room.
[13:54, 14/05/2024] +60 16-837 8881: Noted
[13:58, 14/05/2024] +60 12-559 6863: Azman, u can start early as weekly subcon meeting is cancelled
[13:59, 14/05/2024] Azman HKL: Okay. Noted. NSC, can we start M&E meeting at 2.30pm.
[14:00, 14/05/2024] +60 19-821 8251: Will be late a bit, maybe arrive around 3 sorry
[14:00, 14/05/2024] Azman HKL: 3pm then.
[16:33, 14/05/2024] Azman HKL: 13th floor. Lift shaft opening inspection by Mitsubishi. PL2,

[16:33, 14/05/2024] Azman HKL: PL2, Hotel. Clearing still in progress. Lift shaft not yet ready for verticality checking.

[16:33, 14/05/2024] Azman HKL: 15th floor. Lift motor room. Clearing still in progress.

No comments: