Tuesday, April 30, 2024

30 APRIL 2024 HKL

NSC GROUP 

[08:26, 30/04/2024] Azman HKL: Site progress photo.
30/4/24.
20th floor. TA. Slab support shoring, lift wall rebar, and column rebar in progress.

[08:26, 30/04/2024] Azman HKL: 6th floor. TB5. Slab formwork and beam rebar in progress.

[08:26, 30/04/2024] Azman HKL: 6th floor. TB4. Slab rebar in progress. TB5. Slab formwork and beam rebar in progress.

[08:26, 30/04/2024] Azman HKL: 6th floor. Slab formwork in progress.
[08:50, 30/04/2024] Azman HKL: Morning. Kindly please update and send to me by today M&E NSC progress for this Thursday Meeting. TQ. 🙏🙏@~ShawnChia @HIDAYA KH office Num @Recky Econmech @~sklaw3
[09:03, 30/04/2024] Jimmy HKL: PERINGATAN

Peringatan untuk menghadiri taklimat keselamatan daripada SESB hari ini pada jam 10 pagi di bilik mesyuarat tapak bina PHKL. Mohon hantar seorang wakil untuk hadir. Sekian terima kasih.

[09:19, 30/04/2024] Azman HKL: @~WY @~Rimon Joseph ini macam mana? Confirm tidak sambung sekarang?

[09:42, 30/04/2024] Azman HKL: Man Hole external works in progress.
[09:43, 30/04/2024] +60 14-379 2990: Proceed ja man..

[10:01, 30/04/2024] Azman HKL: Taklimat SESB : PEMASANGAN KESELAMATAN DAN KESEDARAN ELEKTRIK DI KAWASAN LADANG DAN TEMPAT AWAM
 