Monday, April 22, 2024

23 APRIL 2024 HKL

SITE EG MALL 

[10:15, 23/04/2024] Kadapi J. PROMES: @HIDAYA KH office Num Have add bracket to make the verticallity in good condition. Tq
[10:15, 23/04/2024] Kadapi J. PROMES: Level 5
[10:16, 23/04/2024] HIDAYA KH office Num: noted boss. installation still in progress. thank you.



[11:32, 23/04/2024] Kadapi J. PROMES: @HIDAYA KH office Num 
Not acceptable. Please rectify b 4 they back fillbthe area. Our pipe is lower than the main pipe. As i remind b 4, please request for inspection any permenant servicess b 4 any work final done.


NSC GROUP

[08:36, 23/04/2024] Azman HKL: Good morning.
Site progress photo.
23/4/24.
20th floor. TA1. Column rebar in progress

[08:36, 23/04/2024] Azman HKL: 20th floor, TA2. Lift wall, columns and slab support in progress.

[08:37, 23/04/2024] Azman HKL: 6th floor. TB6. Lift wall, ST2 rebar in progress. Slab support in progress.
[09:07, 23/04/2024] Azman HKL: Outstanding M&E room. HKL will catch up to complete this room, 1 by 1. NSC site PIC please also double check and inform me so we can check together. πŸ™

[09:50, 23/04/2024] Azman HKL: 8th floor. Unit 22. Sample unit. As inform. Tunggu dia orang siap tukar pintu dan siap bata dulu baru paip dan ducting opening. @~WY @HIDAYA KH office Num πŸ™

[09:52, 23/04/2024] Azman HKL: 9th floor. @⁨EG Mall DC Raman⁩ @⁨EG Mall Econmech Walkeryapp Yapi⁩ @~zee ini macam mana. Ok sda ka? Kamu ada bincang ka? Kalau ada masalah highlight saya.πŸ‘†

[10:01, 23/04/2024] Azman HKL: 10th floor. @~WY itu pipe sleeve ya. Minta subcon kamucheck semua pasang pipe sleeve. Sini ada yang tiada letak ya.
[10:06, 23/04/2024] +60 14-379 2990: Okay man.
[10:15, 23/04/2024] Azman HKL: @~nas4rie @~Roxas Ng (Kai) @+60 19-802 0222 tolong atur ya sama Joseph atau Joannes untuk. Clearing formwork. πŸ™πŸ™5th floor. Electrical riser.

[10:22, 23/04/2024] Azman HKL: 15th floor. TA1. Wiring in progress.

[10:22, 23/04/2024] Azman HKL: 15th floor. Sprinkler pipe in progress.
[10:38, 23/04/2024] Azman HKL: 14th floor. Wiring and sprinkler pipe works in progress.

[13:10, 23/04/2024] Azman HKL: 20th floor. TA2. Slab progress.

[13:10, 23/04/2024] Azman HKL: 20th floor. TA1. Column progress.

[13:10, 23/04/2024] Azman HKL: 6th floor. TB4. Slab formwork. 7th floor. TB5. Slab formwork.

[14:42, 23/04/2024] Azman HKL: Joint inspection. Cast iron pipe outlet to MH20.

[15:35, 23/04/2024] Azman HKL: @~Leppong πŸ‘†buka formwork. 15th floor.

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...