Sunday, April 14, 2024

15 APRIL 2024 HKL

SITE EG MALL

[09:00, 15/04/2024] +60 18-960 2589: @Azman HKL sini ada laluan trunking elv 2x2 x 2 batang tidak dapat jalan coz ada ducting lekat di lantai,
[09:06, 15/04/2024] Kadapi J. PROMES: Need to discuss with econmech. @Azman HKL Please 
arrange site coordination meeting on site.
[09:09, 15/04/2024] Azman HKL: @~zee  refer coordination drawing. Kita agree, patut ada ruang untuk trunking..πŸ‘†@~WY tolong cek sama kamu punya subcon kalau boleh bagi ruang untuk ELV.
[09:11, 15/04/2024] +60 14-379 2990: Boleh check jarak junction box elv dari wall?
[09:14, 15/04/2024] Kadapi J. PROMES: Dear NSC's, please follow coordination given by hkl. Do not simply apply whos 1st got placed. We have prepared coordination as per-discussed with u all. Tq
[09:22, 15/04/2024] +60 14-379 2990: Noted.
[10:43, 15/04/2024] Kadapi J. PROMES: @~WY ,@~zee ,@Azman HKL Please come for site coordination discussion at level 8 hotel in 2.30pm. The coordination between the clashed of the elv trunking and ducting installation.tq

[11:07, 15/04/2024] +60 16-880 4632: Nosing tile deliver to site.at ground floor
[11:24, 15/04/2024] Kadapi J. PROMES: Tiada orang reply? Mau datang atau tidak owhh.
[11:26, 15/04/2024] +60 18-960 2589: ok tuan, saya kesana masa yg di tetapkan, maaf lambat respon ada kerja sikit,
[11:32, 15/04/2024] Azman HKL: 2.30pm meet at ground floor.. πŸ‘Œ

[15:38, 15/04/2024] Azman HKL: @~zee cek ini kalau dapat jalan trunking ELV. Imut kuning sama hijau. Kasi ejas itu point masuk trunking ikut itu line..
[15:38, 15/04/2024] Azman HKL: Try ejas dulu onsite ya.
[15:40, 15/04/2024] +60 18-960 2589: ya, mcm ni jalan lah ngam,



[15:40, 15/04/2024] Azman HKL: @~WY @~zee tolong ya. Sama2 kamu check. Ducting dgn Trunking tu.. πŸ‘†
[15:55, 15/04/2024] Azman HKL: Bah. Bila kamu maw start ni? Barang kamu ada sudah?
[15:56, 15/04/2024] +60 18-960 2589: minggu ini juga, ada sikit barang lagi belum ada,
[16:01, 15/04/2024] Azman HKL: Okay. Bubut dia. Kita kasi settle cepat supaya boleh cek awal coordination. Baru kita dapat naik atas floor.
[16:52, 15/04/2024] +60 18-960 2589: Ok man.

 NSC GROUP

[08:27, 15/04/2024] Azman HKL: Site progress photo.
15/04/24
20th floor. TA1. 
Slab formwork and column rebar in progress

[08:27, 15/04/2024] Azman HKL: 5th floor. TB6. Slab formwork and lift wall rebar in progress.

[08:35, 15/04/2024] Azman HKL: Monday morning safety toolbox briefing..

[08:54, 15/04/2024] EG MALL Mr Lo: MH20 sedang korek, king Hong you punya paip ?
[08:55, 15/04/2024] EG MALL Mr Lo: @HIDAYA KH office Num

[08:58, 15/04/2024] EG MALL Mr Lo: πŸ‘

[09:32, 15/04/2024] Azman HKL: @Azman HKL tolong dulu ini pipe di level 8 unit 24
[09:33, 15/04/2024] Azman HKL: @Leung KHπŸ€ tolong check sama archi team di 8th floor. Ini kena itu wall..


[09:47, 15/04/2024] Azman HKL: Ground floor. MH20. Outlet pipe Sanitary and RWDP excavation in progress.

[09:48, 15/04/2024] Leung KHπŸ€: πŸ‘ŒπŸ»

[09:52, 15/04/2024] Azman HKL: Basement. Cable tray bracket in progress.

[09:55, 15/04/2024] Azman HKL: Ground floor. HV room. @~WY @~Rimon Joseph ini bilik ada lagi kamu maw buat? Kalau ok sudah tolong kejar dia tutup itu semua lobang2 di wall sebelum finishing. πŸ™
[09:56, 15/04/2024] +60 14-379 2990: Okay man


[10:00, 15/04/2024] Azman HKL: HV room. DCC unboxing switchgear and inspection in progress.
[10:03, 15/04/2024] +60 12-559 6863: Azman, lepas kerja suruh housekeeping ya
[10:04, 15/04/2024] Azman HKL: Iya bos. @~Leppong @~s4yamahuk4ya88.gmail.com housekeeping nanti bekas kerja.πŸ™
[10:06, 15/04/2024] Azman HKL: @~WY tolong double check juga ya kamu punya box opening kalau terkena.πŸ™


[10:38, 15/04/2024] Leung KHπŸ€: Level 3 - Incoming CW Pipe

[10:38, 15/04/2024] Leung KHπŸ€: Level 3 - Rectify FRP Cold Water Storage Tank Plinth

[10:38, 15/04/2024] Leung KHπŸ€: Level 8 - Hotel Room Wash Basin Pipe
[10:40, 15/04/2024] Mr. Voo: Hack ? Not coring ?
[10:41, 15/04/2024] +60 12-559 6863: Dear all, as we informed earlier, no hacking to hotel slab is allowed, only coring please
[10:46, 15/04/2024] Edwin Chen 013: @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” @Mr. Voo , Please teach me how to lay pipe if no hacking allow
[10:47, 15/04/2024] +60 12-559 6863: Lay what pipe? How deep?
[10:47, 15/04/2024] Mr. Voo: We talking about slab
[10:47, 15/04/2024] Mr. Voo: Brick wall hack saja
[10:47, 15/04/2024] +60 12-559 6863: We already mentioned earlier, any hacking need to pre inform as we need to consult our PE
[10:50, 15/04/2024] Edwin Chen 013: Hello. This is wall brick
[10:50, 15/04/2024] Mr. Voo: Ok loh if brick wall


[14:17, 15/04/2024] Azman HKL: HV room, Switchgear unboxing.

[14:49, 15/04/2024] Azman HKL: @EG MALL Mr Lo @Edwin Chen 013 @Leung KHπŸ€ @HIDAYA KH office Num 3rd floor pump room. Ini pipe sleeve Floor trap scupper drain. Kita buka la ya. Air bertakung.
[14:50, 15/04/2024] Azman HKL: @Leung KHπŸ€ kalau ada orang nanti minta tolong buka la ini ya. Air tidak dapat keluar..
[14:57, 15/04/2024] Edwin Chen 013: @Leung KHπŸ€, please arrange and cut the top part of the pipe sleeve.

[14:58, 15/04/2024] Azman HKL: @Azman HKL 14F kana sudah ko punya pipe πŸ˜…
[14:59, 15/04/2024] Azman HKL: @Leung KHπŸ€ @HIDAYA KH office Num sini sama juga. Nanti tolong cek ya. Biar mereka marking dulu, then kamu cepat2 tolong cek/atur dia.
[15:02, 15/04/2024] Leung KHπŸ€: Noted
[15:02, 15/04/2024] Leung KHπŸ€: Okay

[15:24, 15/04/2024] Azman HKL: @Leung KHπŸ€ tolong kejar 8th floor slab coring. Kita target dia ini minggu siap. πŸ™.
[15:24, 15/04/2024] +60 12-559 6863: kalao HKL buat kena charge ya
[15:24, 15/04/2024] Azman HKL: Opening bah.. πŸ‘†πŸ˜…
[15:25, 15/04/2024] +60 12-559 6863: sepatutnya kamu  ada timber frame situ
[15:26, 15/04/2024] EG MALL ECONMECH Dart: timber frame utk kecik bole la bos raymond. if besar ni mau ada lintel beam sepatutnya. sy cba atur this week.
[15:27, 15/04/2024] +60 12-559 6863: ini kira besar kah?
[15:27, 15/04/2024] +60 12-559 6863: pakai timber 1/2 inchi buat itu frame

[15:27, 15/04/2024] Azman HKL: @Leung KHπŸ€ Ini semua maw tutup kan. Linen room. Tiada sdah bilik riser sini. Tolong inform org kamu nanti ya. Alang2 satu kali mereka tutup.. 🫰
[15:28, 15/04/2024] EG MALL ECONMECH Dart: bha kami try buat dulu sample.

[15:29, 15/04/2024] Azman HKL: @Leung KHπŸ€ Please check. πŸ™

[15:32, 15/04/2024] Azman HKL: 8th floor.

[15:32, 15/04/2024] Azman HKL: 8th floor. Sample unit
[15:32, 15/04/2024] Azman HKL: Sample unit. @~WY itu opening kalau ngam sdah terus tutup la. Jangan biar lama2 tukang cat masuk.. πŸ™
[15:35, 15/04/2024] Azman HKL: Sementara ada orang buat plastering sini. Banyak simen boleh pakai.
[15:38, 15/04/2024] +60 12-559 6863: @Azman HKL kalao Econmech minta HKL tolong buat, suruh tulis surat dan kita akan bagi quotation
[15:39, 15/04/2024] +60 12-559 6863: termasuk itu timber box
[15:39, 15/04/2024] EG MALL ECONMECH Dart: Ni wall mau scheme coat lagi ka boss raymond?
[15:39, 15/04/2024] +60 12-559 6863: belum tau
[15:43, 15/04/2024] Azman HKL: Iya. Noted.

[15:46, 15/04/2024] Azman HKL: Okay. TQ boss.. πŸ™πŸ˜…
[15:50, 15/04/2024] EG MALL Mr Lo: flat slab 21st floor, please check m n e services void match


[16:00, 15/04/2024] Azman HKL: 8th floor. Unit 23/24 riser room. @~WY ada kena bata itu box opening sama riser pipe sleeve. Tolong cek dia. Bincang sama supervisor archi. Bsok mereka maw jalan bata.

[16:10, 15/04/2024] Azman HKL: 8th floor. Electrical riser room. @⁨PHKL APM Tan....⁩ @⁨EG Mall Roxas Ng (Kai)⁩ tolong push archi kejar ini bilik ya untuk sample riser.πŸ™ Brick and plastering.

[16:10, 15/04/2024] Azman HKL: 8th floor. 20/21 riser room. Plaster wall.

[16:10, 15/04/2024] Azman HKL: 22 riser room. Wall plaster and brick
[16:10, 15/04/2024] Azman HKL: @~.... @~Roxas Ng (Kai)
[16:12, 15/04/2024] +60 16-239 9318: Noted

[16:15, 15/04/2024] Azman HKL: 5th floor. TB6. Slab rebar in progress.

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...