SITE EG MALL
[09:49, 08/04/2024] Azman HKL: Site progress photo.
8/4/24.
19th floor. TA1. Slab cast.
[09:50, 08/04/2024] Azman HKL: 7th floor. TB3. Slab cast.
[09:50, 08/04/2024] Azman HKL: 7th floor. Wiring work and ducting work in progress.
[09:50, 08/04/2024] Azman HKL: 8th floor. TA. Electrical conduit installation at brick wall in progress.
[09:50, 08/04/2024] Azman HKL: 8th floor. TA. Plumbing pipe at a high level in progress.
NSC GROUP
[08:27, 08/04/2024] Azman HKL: NSC Morning safety toolbox.
[09:23, 08/04/2024] Azman HKL: Ground floor. AHU Temporary storage at ground floor.
[09:23, 08/04/2024] Azman HKL: Ground floor. FCU temporary storage at ground floor.
[09:24, 08/04/2024] Azman HKL: HV room at ground floor. Door done installation. @~ShawnChia ๐.
[09:30, 08/04/2024] Azman HKL: Site progress photo.
8/4/24.
19th floor. TA1. Slab cast.
[09:30, 08/04/2024] Azman HKL: 7th floor. TB3. Slab cast.
[09:30, 08/04/2024] Azman HKL: 7th floor. Wiring work and ducting work in progress.
[09:36, 08/04/2024] Azman HKL: @~Leppong @~WY @HIDAYA KH office Num @~zee share gambar ya mana kamu ada kerja ini hari. ๐๐
[09:39, 08/04/2024] +60 17-866 0355: ๐
[09:48, 08/04/2024] Azman HKL: 8th floor. TA. Electrical conduit installation at brick wall in progress.
[09:49, 08/04/2024] Azman HKL: 8th floor. TA. Plumbing pipe at a high level in progress.
[09:58, 08/04/2024] Leung KH๐: Level 3 - Rectify FRP Cold Water Storage Tank Plinth
[10:32, 08/04/2024] Azman HKL: 11th floor. TA. Electrical trunking in progress.
[10:32, 08/04/2024] Azman HKL: 12th floor. ST6 wiring in progress
[10:32, 08/04/2024] Azman HKL: 12th floor. TA. Electrical trunking in progress.
[10:34, 08/04/2024] Azman HKL: 13th floor. TA. Sprinkler pipe in progress.
[10:34, 08/04/2024] +60 12-559 6863: mana safety?
[10:35, 08/04/2024] +60 12-559 6863: pakai scaffolding bah
[11:42, 08/04/2024] Azman HKL: Ground floor. Lift shaft.clear.
[11:42, 08/04/2024] Azman HKL: Lift shaft PL1. Hotel
[11:42, 08/04/2024] Azman HKL: Lift shaft PL2.
[11:43, 08/04/2024] Azman HKL: @~YoonYK later please check together if got any obstruction. Got some water inside we will arrange to pump out..๐
[11:45, 08/04/2024] Azman HKL: Ground floor. Sprinkler pipe riser. @~WY nanti tolong cek ini riser room. Ada banyak air masuk dari atas. Kalau dapat tutup dia supaya air tidak masuk dalam. Itu cat di wall sda luntur..
[11:45, 08/04/2024] +60 19-821 8251: Ok will do.
[11:48, 08/04/2024] +60 16-832 2597: Team M&E boleh tlg tutup ni lubang? Dari 1F sana block dia, ada air masuk sudah bilik riser dekat ST08
[11:49, 08/04/2024] +60 16-832 2597: @Azman HKL siapa punya lubang ni ya?
[11:59, 08/04/2024] Azman HKL: Electrical riser. Dekat ST09 itu. @~Leppong @~.Fazli nanti tolong cek dia. Tgk itu air masuk dari opening. Tolong kalau dapat tutup dia. ๐๐
[12:00, 08/04/2024] Azman HKL: TQ inform. ๐
[13:38, 08/04/2024] +60 12-843 3877: Level berapa?
[13:42, 08/04/2024] Azman HKL: Tgk sana electrical riser, ST09. Ground floor. Tolong cek dia.
[14:00, 08/04/2024] +60 12-843 3877: Itu air bukan dari level 6 kah?
[15:05, 08/04/2024] Azman HKL: @~nas4rie ๐belum ready ni..
[15:06, 08/04/2024] Azman HKL: 4th floor. TB6. ๐
[15:08, 08/04/2024] Azman HKL: @~nas4rie Tolong kejar dulu confirm bila boleh inspection. ๐๐.
[15:17, 08/04/2024] Azman HKL: Scupper drain flow trap at parking floor @EG MALL Mr Lo @Leung KH๐ @Edwin Chen 013 . Request for your permission. Kami maw buka itu pipe floor trap untuk buang air betakung di sana. Kalau maybe next week kami start buka dia.
[15:19, 08/04/2024] Azman HKL: Flow trap. ๐. Kami sambung paip untuk buang air..
[15:21, 08/04/2024] Edwin Chen 013: Sambung?
[15:28, 08/04/2024] Azman HKL: Lebih kurang macam begini..
[15:29, 08/04/2024] Mr. Voo: Supaya dpt detect flood issue
No comments:
Post a Comment