08 APRIL 2024 HKL

SITE EG MALL

[09:49, 08/04/2024] Azman HKL: Site progress photo.
8/4/24.
19th floor. TA1. Slab cast.

[09:50, 08/04/2024] Azman HKL: 7th floor. TB3. Slab cast.

[09:50, 08/04/2024] Azman HKL: 7th floor. Wiring work and ducting work in progress.

[09:50, 08/04/2024] Azman HKL: 8th floor. TA. Electrical conduit installation at brick wall in progress.

[09:50, 08/04/2024] Azman HKL: 8th floor. TA. Plumbing pipe at a high level in progress.


 NSC GROUP 

[08:27, 08/04/2024] Azman HKL: NSC Morning safety toolbox.

[09:23, 08/04/2024] Azman HKL: Ground floor. AHU Temporary storage at ground floor.

[09:23, 08/04/2024] Azman HKL: Ground floor. FCU temporary storage at ground floor.

[09:24, 08/04/2024] Azman HKL: HV room at ground floor. Door done installation. @~ShawnChia ๐Ÿ‘†.

[09:30, 08/04/2024] Azman HKL: Site progress photo.
8/4/24.
19th floor. TA1. Slab cast.

[09:30, 08/04/2024] Azman HKL: 7th floor. TB3. Slab cast.

[09:30, 08/04/2024] Azman HKL: 7th floor. Wiring work and ducting work in progress.
[09:36, 08/04/2024] Azman HKL: @~Leppong @~WY @HIDAYA KH office Num @~zee share gambar ya mana kamu ada kerja ini hari. ๐Ÿ™๐Ÿ™
[09:39, 08/04/2024] +60 17-866 0355: ๐Ÿ‘Œ

[09:48, 08/04/2024] Azman HKL: 8th floor. TA. Electrical conduit installation at brick wall in progress.


[09:49, 08/04/2024] Azman HKL: 8th floor. TA. Plumbing pipe at a high level in progress.

[09:58, 08/04/2024] Leung KH๐Ÿ€: Level 3 - Rectify FRP Cold Water Storage Tank Plinth

[10:32, 08/04/2024] Azman HKL: 11th floor. TA. Electrical trunking in progress.

[10:32, 08/04/2024] Azman HKL: 12th floor. ST6 wiring in progress

[10:32, 08/04/2024] Azman HKL: 12th floor. TA. Electrical trunking in progress.

[10:34, 08/04/2024] Azman HKL: 13th floor. TA. Sprinkler pipe in progress.
[10:34, 08/04/2024] +60 12-559 6863: mana safety?
[10:35, 08/04/2024] +60 12-559 6863: pakai scaffolding bah

[11:42, 08/04/2024] Azman HKL: Ground floor. Lift shaft.clear.

[11:42, 08/04/2024] Azman HKL: Lift shaft PL1. Hotel

[11:42, 08/04/2024] Azman HKL: Lift shaft PL2.
[11:43, 08/04/2024] Azman HKL: @~YoonYK later please check together if got any obstruction. Got some water inside we will arrange to pump out..๐Ÿ‘†

[11:45, 08/04/2024] Azman HKL: Ground floor. Sprinkler pipe riser. @~WY nanti tolong cek ini riser room. Ada banyak air masuk dari atas. Kalau dapat tutup dia supaya air tidak masuk dalam. Itu cat di wall sda luntur..
[11:45, 08/04/2024] +60 19-821 8251: Ok will do.
[11:48, 08/04/2024] +60 16-832 2597: Team M&E boleh tlg tutup ni lubang? Dari 1F sana block dia, ada air masuk sudah bilik riser dekat ST08

[11:49, 08/04/2024] +60 16-832 2597: @Azman HKL siapa punya lubang ni ya?
[11:59, 08/04/2024] Azman HKL: Electrical riser. Dekat ST09 itu. @~Leppong @~.Fazli  nanti tolong cek dia. Tgk itu air masuk dari opening. Tolong kalau dapat tutup dia. ๐Ÿ™๐Ÿ™
[12:00, 08/04/2024] Azman HKL: TQ inform. ๐Ÿ‘Œ
[13:38, 08/04/2024] +60 12-843 3877: Level berapa?
[13:42, 08/04/2024] Azman HKL: Tgk sana electrical riser, ST09. Ground floor. Tolong cek dia.
[14:00, 08/04/2024] +60 12-843 3877: Itu air bukan dari level 6 kah?
[15:05, 08/04/2024] Azman HKL: @~nas4rie ๐Ÿ‘†belum ready ni..

[15:06, 08/04/2024] Azman HKL: 4th floor. TB6. ๐Ÿ‘†
[15:08, 08/04/2024] Azman HKL: @~nas4rie Tolong kejar dulu confirm bila boleh inspection. ๐Ÿ‘†๐Ÿ™.


[15:17, 08/04/2024] Azman HKL: Scupper drain flow trap at parking floor @EG MALL Mr Lo @Leung KH๐Ÿ€ @Edwin Chen 013 . Request for your permission. Kami maw buka itu pipe floor trap untuk buang air betakung di sana. Kalau maybe next week kami start buka dia.

[15:19, 08/04/2024] Azman HKL: Flow trap. ๐Ÿ‘†. Kami sambung paip untuk buang air..
[15:21, 08/04/2024] Edwin Chen 013: Sambung?
[15:23, 08/04/2024] Azman HKL: Temporary, tidak gam. Supaya air boleh tolak buang keluar saja.
[15:26, 08/04/2024] EG MALL Mr Lo: Ok ๐Ÿ‘Œ

[15:28, 08/04/2024] Azman HKL: Lebih kurang macam begini..
[15:29, 08/04/2024] Mr. Voo: Supaya dpt detect flood issue