Saturday, April 6, 2024

07 APRIL 2024 HKL

SITE EG MALL

[09:54, 07/04/2024] Azman HKL: 19th floor. TA2. Currently work in progress but the casting plan at 12pm. We request for M&E inspection at 11.30am. @⁨Kadapi J. EG Mall Promess Gadapi⁩ . πŸ™to all NSC PIC please stand by at site during inspection. @Leung KHπŸ€ @~zee @~Leppong @~WY πŸ™πŸ™
[09:55, 07/04/2024] Azman HKL: @Kadapi J. PROMES

[11:45, 07/04/2024] Kadapi J. PROMES: This area no bar yet?
[11:48, 07/04/2024] Kadapi J. PROMES: @Azman HKL @~nas4rie @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘”
[11:49, 07/04/2024] Kadapi J. PROMES: Most of the area still laying 2nd layer bar reinforcement
[12:09, 07/04/2024] +60 12-559 6863: Working non stop now to get ready
[12:11, 07/04/2024] Kadapi J. PROMES: I will update within 1/2 hourπŸ˜…





[13:21, 07/04/2024] Azman HKL: 19th floor. TA2. Some slab rebar and M&E in progress


[13:23, 07/04/2024] Kadapi J. PROMES: U can start cast in this area uf u want

[13:24, 07/04/2024] Kadapi J. PROMES: Our mne progressively at this area
[13:27, 07/04/2024] Kadapi J. PROMES: Just pending for rebar works to install our mne conduits
[13:31, 07/04/2024] +60 12-833 6147: Pls take note.

[14:00, 07/04/2024] Kadapi J. PROMES: MnE conduit, opening for DB, ELV & TEL csn not install yet due to formwork and rebar not yet done at this electrical room

[14:01, 07/04/2024] Kadapi J. PROMES: ELECTRICAL ROOM/RISER
[14:08, 07/04/2024] Kadapi J. PROMES: MnE r done accept at this area and pending for formworks and rebar work


[15:16, 07/04/2024] Azman HKL: @Azman HKL itu M&E riser mau siap sudah tu besi
[15:20, 07/04/2024] Kadapi J. PROMES: πŸ‘ŒπŸ‘ aku turun sdh. D site opis ni tunggu hujan reda baru pulangπŸ˜…

[15:55, 07/04/2024] Kadapi J. PROMES: Hujan lebat lorrr
[15:58, 07/04/2024] Azman HKL: Iya bosku. Tunggu reda hujan.

[17:40, 07/04/2024] Azman HKL: 19th floor. All M&E inspection done. @Mr. Voo please proceed. πŸ‘Œ

 NSC GROUP 

[08:06, 07/04/2024] Azman HKL: Morning. 
Site progress photo.
7/4/24.
19th floor. TA2. Slab rebar and formwork in progress.

[08:23, 07/04/2024] +60 12-559 6863: Dear all, kindly start your works early at TA/2 19F in order to start casting at 12noon ya, thank u for your cooperation πŸ™

[08:29, 07/04/2024] Azman HKL: 4th floor. ST02, RC wall formwork in progress.
[08:43, 07/04/2024] Azman HKL: @~Leppong @~ShawnChia @~Rimon Joseph @~zee tolong ya. Lantai TA2. Kena kejar laju ni hari. Konkrit ada masa untuk kita jam 12pm. πŸ™πŸ™. Kami push subcon C&S juga supaya boleh bagi kamu jalan M&E ya. πŸ™πŸ™. Ada apa masalah inform sini kjta kasi selesai..

[08:48, 07/04/2024] Azman HKL: 19th floor. TA2. Conduit installation in progress.
[08:50, 07/04/2024] Azman HKL: @~zee ELV @~Rimon Joseph FP & ACMV, ambil gambar workers kamu di atas ya. Share di sini. πŸ™πŸ™

[08:52, 07/04/2024] Azman HKL: 19th floor. TA2.
[08:54, 07/04/2024] +60 18-960 2589: baru start ini hari, kemarin hujan,
[09:00, 07/04/2024] Azman HKL: Iya. Minta tolong ni hari ya. πŸ™.
[09:06, 07/04/2024] +60 17-866 0355: @Azman HKL  19 TA2 tidak dapat kalau 12 pm maw  casting sebab M&E baru star ni pagi tidak dapat stenga hari
[09:10, 07/04/2024] Azman HKL: Iya faham. Cuba dulu mana yang boleh pasang kasi siap dia. Cuba dulu habis baik. πŸ™..
[09:12, 07/04/2024] Azman HKL: @~ShawnChia tolong juga ya. Kita cuba. Sebab next week banyak cuti raya kita akan kurang progress. Minta kita sama2 kejar dia ni hari. πŸ™πŸ™ Saya akan minta push subcon juga kasi siap itu slab formwork sama rebar.. πŸ™
[09:21, 07/04/2024] +60 16-837 8881: Kita sama sama usaha
[09:22, 07/04/2024] Azman HKL: Tq very much. πŸ’ͺ
[09:24, 07/04/2024] +60 18-960 2589: ia kawan,
[09:25, 07/04/2024] +60 18-960 2589: Ok tuan,
[09:56, 07/04/2024] Azman HKL: @~Rimon Joseph @EG MALL ECONMECH Dart minta gambar. πŸ™
[11:11, 07/04/2024] +60 19-809 6068: Installation opening for Sprinkler, Hosereel and Wet Riser in progress 19th floor
[11:16, 07/04/2024] +60 17-866 0355: @Azman HKL  bilik electrical belum ada lantai pipe tidak dapat sambung
[11:19, 07/04/2024] +60 17-866 0355: @Azman HKL  tinggal 1 jam kita punya masa πŸ™
[11:20, 07/04/2024] +60 19-809 6068: Install pipe sleeve for Hosereel in progress 19th floor.
[11:24, 07/04/2024] +60 19-809 6068: Installation conduit for fire alarm in progress 19th floor.
[11:56, 07/04/2024] Azman HKL: Iya. Saya kejar subcon kasi buat dia. TQ inform.

[12:16, 07/04/2024] Azman HKL: Sedang pasang @~Leppong πŸ‘†




[12:23, 07/04/2024] +60 17-866 0355: @Azman HKL  bilik electrical masih belum ada lantai
[12:27, 07/04/2024] Azman HKL: @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” ini bos. Urgent minta tolong. Banyak konduit sama ada slab opening. Minta tolong subcon kita supaya inspection pass. πŸ™πŸ™
[13:02, 07/04/2024] +60 12-559 6863: @Azman HKL kita start dulu dari G/L 4 situ semasa tunggu siap yg ruser sana, tolong inform Kadapi ya
[13:14, 07/04/2024] Azman HKL: πŸ‘Œ

[13:21, 07/04/2024] Azman HKL: 19th floor. TA2. Some slab rebar and M&E in progress


[15:16, 07/04/2024] Azman HKL: @Azman HKL itu M&E riser mau siap sudah tu besi
[15:17, 07/04/2024] Azman HKL: @~Leppong πŸ‘†πŸ™

[17:40, 07/04/2024] Azman HKL: 19th floor. All M&E inspection done. @Mr. Voo please proceed. πŸ‘Œ
[17:49, 07/04/2024] +60 12-559 6863: Thanks all for the hard work and understandingπŸ™ really appreciate it