[09:58, 03/04/2024] Azman HKL: 1st floor. Cold water pipe and Sanitary Pipe inspection with consultant.
[10:01, 03/04/2024] Azman HKL: Sanitary pipe inspection. π
[10:05, 03/04/2024] Azman HKL: Cold water pipe inspection.
NSC GROUP
[6:58 am, 03/04/2024] Azman HKL: Morning. NSC tolong update latest work progress ini hari ya untuk meeting bsok..π
[8:56 am, 03/04/2024] Azman HKL: Site progress photo.
3/4/24
7th floor. TB3. Slab formwork and beam rebar in progress.
[8:56 am, 03/04/2024] Azman HKL: 19th floor. TA2. Slab formwork in progress.
[8:56 am, 03/04/2024] Azman HKL: 5th floor. TB6. Slab formwork and support in progress.
[8:56 am, 03/04/2024] Azman HKL: Earthwork in progress.
[9:25 am, 03/04/2024] Edwin Chen 013: @~π
πΆπ ππ½πππ @Mr. Voo @~Roxas Ng (Kai) we will start our works on the levelling on the tank plinth as per our discussion.
[9:26 am, 03/04/2024] Mr. Voo: ππΏ
[9:26 am, 03/04/2024] Mr. Voo: @Azman HKL take record plz
[9:30 am, 03/04/2024] Azman HKL: Ok.
[9:59 am, 03/04/2024] Azman HKL: 1st floor. Cold water pipe and Sanitary Pipe inspection with consultant.
[10:01 am, 03/04/2024] Azman HKL: Sanitary pipe inspection. π
[10:53 am, 03/04/2024] Azman HKL: SSF inspection. Temporary storage at the Ground floor.
[10:58 am, 03/04/2024] Azman HKL: Basement. Cable tray. π
[11:12 am, 03/04/2024] Azman HKL: Outlet pipe to Man hole. π
[11:18 am, 03/04/2024] +60 12-559 6863: @EG MALL Mr Lo need to encase?
[11:19 am, 03/04/2024] EG MALL Mr Lo: any pipe under the road section need to encase with concrete
[11:20 am, 03/04/2024] Azman HKL: @HIDAYA KH office Num @Edwin Chen 013 bagus pasang paip kamu dan tutup sekali. Cek kamu punya paip kalau perlu encase. ππ
[11:20 am, 03/04/2024] Azman HKL: Jangan kasi lama.
[11:22 am, 03/04/2024] HIDAYA KH office Num: okay azman
[11:37 am, 03/04/2024] Azman HKL: @~WY @HIDAYA KH office Num ini dua riser ada apa2 outstanding lagi? Kalau ada slab opening lama tidak pakai tolong kasi tutup dia cepat ya supaya tidak kacau tukang bata. π
[11:38 am, 03/04/2024] Azman HKL: Saya maw archi start plaster riser wall supaya kita boleh pasang itu paip sama duct di sample room.π
[11:43 am, 03/04/2024] HIDAYA KH office Num: okay
[3:18 pm, 03/04/2024] Azman HKL: 19th floor. TA2. Slab formwork in progress
[3:18 pm, 03/04/2024] Azman HKL: 7th floor. TB3. Slab formwork and beam rebar.
[3:28 pm, 03/04/2024] Azman HKL: ππ»ππ»
[3:32 pm, 03/04/2024] Azman HKL: 3rd floor. Water tank. @HIDAYA KH office Num ini 3 orang KH buat clearing ka? Tiada orang GnB buat clearing?
[3:34 pm, 03/04/2024] Azman HKL: @Mr. Voo @~π
πΆπ ππ½πππ @Edwin Chen 013 macam mana kira ini? Sign kong harian atau leveling plinth saja?
[3:35 pm, 03/04/2024] Azman HKL: @HIDAYA KH office Num Ini GnB yang buat atau KH?
[3:35 pm, 03/04/2024] HIDAYA KH office Num: iyaa. orang kami sendiri tu tolak tepi batu2 tu tadi
[3:36 pm, 03/04/2024] HIDAYA KH office Num: ya ini la ni lepas tolak tepi semua batu2 tu
[3:36 pm, 03/04/2024] HIDAYA KH office Num: yg ini GNB
[3:43 pm, 03/04/2024] Azman HKL: Ok