SITE EG MALL

[10:29, 28/03/2024] Azman HKL: Ground floor. Joint inspection. @~s4yamahuk4ya88.gmail.com @HIDAYA KH office Num @Kadapi J. PROMES .

[10:30, 28/03/2024] Azman HKL: Chiller temporary storage in the Basement.

[10:40, 28/03/2024] Azman HKL: Electrical joint inspection at ground floor.
[10:49, 28/03/2024] Azman HKL: Ground floor. Cold water and Sanitary pipe inspection.



[14:28, 28/03/2024] +60 16-832 2597: 14F ST06 inspection setting out for Bricks

[14:57, 28/03/2024] +60 16-832 2597: 14F inspection for office room brick setting out

[14:58, 28/03/2024] +60 16-832 2597: 14F inspection for MSB brick setting out

[15:20, 28/03/2024] +60 16-832 2597: 14F inspection for MSB room’s Riser room brick setting out
[16:51, 28/03/2024] EG MALL ECONMECH Dart: @~YoonYK Can u check yr hotel lift pit exhaust where do u discharge on 15F?
[16:52, 28/03/2024] +60 19-821 8251: @Azman HKL boleh tolong check rfi ada reply kah? 😶
[16:53, 28/03/2024] EG MALL ECONMECH Dart: Brapa cfm yoon?
[16:55, 28/03/2024] Azman HKL: Macam tiada. Nanti saya cek balik.
[17:06, 28/03/2024] +60 19-821 8251: Berapa confirm?
[17:07, 28/03/2024] +60 19-821 8251: Ok thanks. 🙏

[17:09, 28/03/2024] EG MALL ECONMECH Dart: Nt stdy yoon. Rsanya kna ducted tu
[17:09, 28/03/2024] +60 16-880 4632: ST06 Brickwork no objection to proceed. 
STO5 GLH/4-4a
Riser wall no objection to proceed..
Conditions at L14 debris to clear...it obstructing our inspection..rebar at floor to remove..
[17:09, 28/03/2024] +60 19-821 8251: Okok 🙏


[17:14, 28/03/2024] +60 16-880 4632: @~Roxas Ng (Kai) 
Please check your attachments for inspection L14.


[17:19, 28/03/2024] +60 16-880 4632: Office brick wall 
On hold ST06 column off by 230mm..Still pending ABLT advice..

 NSC GROUP 

[08:55, 28/03/2024] Azman HKL: Site progress photo.
28/3/24.
19th floor. TA1. Slab formwork, rebar no progress. TA2. Lift wall and column rebar no progress.

[08:55, 28/03/2024] Azman HKL: 5th floor, TB6. Slab support and lift wall rebar.

[08:55, 28/03/2024] Azman HKL: 7th floor.  TB3. Slab formwork.

[08:56, 28/03/2024] Azman HKL: 3 nos of chiller temporary stores in the basement.

[08:57, 28/03/2024] Azman HKL: 1st floor, lift shaft clearing in progress.

[09:50, 28/03/2024] Azman HKL: HV ROOM. Tatai done.

[09:51, 28/03/2024] Azman HKL: Chiller temporary store in the Basement.
[13:19, 28/03/2024] +60 16-837 8881: Tq
[13:22, 28/03/2024] HIDAYA KH office Num: @Azman HKL  casting date untuk 19th floor TA1&TA2 ada perubahan ka?
[13:24, 28/03/2024] Azman HKL: Site condition. Casting plan is on this Monday. 🙏