[08:28, 20/03/2024] Azman HKL: Site progress photo.
20/3/24.
18th floor. TA1. Slab formwork and rebar in progress.
[08:30, 20/03/2024] Azman HKL: 4th floor. TB6. Slab formwork and 3rd floor lift wall rebar in progress.
[08:30, 20/03/2024] Azman HKL: Basement. Earthwork in progress.
[09:08, 20/03/2024] Azman HKL: To all dear NSC Site PIC. As per the discussion of yesterday's meeting, any site urgent issue needs to be solved, Please share at this group and tag my name. Me and the HKL team will try to solve it 1 by 1. For coordination/technical issues please share it at the Coordination Group Whatsapp. 🙏
[10:24, 20/03/2024] Azman HKL: Joint inspection with econmech, Chiller supplier, lorry operator. To coordinate Chiller delivery to site at basement.
[10:28, 20/03/2024] Azman HKL: Econmech requests temporary storage for their 3nos chiller this area.
[10:30, 20/03/2024] +60 12-559 6863: coordinate sama GNB kasi clear ini tempat untuk dorang
[10:46, 20/03/2024] Azman HKL: Iya bos.
[10:53, 20/03/2024] Azman HKL: 1st floor. AHU room sudah clear. @~WY tolong marking dia AHU plinth. Saya maw kejar subcon pasang formwork.
[10:54, 20/03/2024] +60 14-379 2990: Ok man.
[10:54, 20/03/2024] Azman HKL: Tu scaffolding biar saja asal kamu dapat marking di lantai saja.
[15:03, 20/03/2024] Azman HKL: 18th floor. TA1. M&E Inspection with. Consultant at 3.30pm. NSC PIC please stand by the site during inspection.
[15:42, 20/03/2024] Azman HKL: Selepas kerja ni, konduit tolong kasi bersih semua tu sampah kita ya. Itu conduit tidak pakai tolong kasi kumpul buang di tempah sampah di bawah.