Monday, March 18, 2024

18 MAC 2024 HKL

SITE EG MALL


[10:32, 18/03/2024] +60 16-880 4632: L13

[10:33, 18/03/2024] +60 16-880 4632: L13

[10:35, 18/03/2024] +60 16-880 4632: L13




NSC GROUP 

[08:13, 18/03/2024] Azman HKL: Good morning. 
NSC Safety tool box. 8.30am, every monday at the ground floor. All NSC workers must join. TQ. 👆
[08:18, 18/03/2024] Azman HKL: Good morning. 
Site progress photo.
18/3/24.
18th floor. TA1. Slab formwork in progress.

[08:18, 18/03/2024] Azman HKL: 18th floor. TA2. Lift wall formwork, column formwork in progress.

[08:18, 18/03/2024] Azman HKL: 3rd floor. TB4. Slab/beam support in progress. Lift wall rebar in progress.

[08:32, 18/03/2024] Azman HKL: Safety tool box.
[09:14, 18/03/2024] EG MALL ECONMECH Dart: Morning. @EG MALL Mr Lo u hv latest drawing from archi tower A Roof floor level ? C&s dwg also

[09:31, 18/03/2024] Azman HKL: Basement fire tank installation in progress.

[09:31, 18/03/2024] Azman HKL: Basement fire tank.
[09:33, 18/03/2024] EG MALL Mr Lo: no for structure Archi got
[09:33, 18/03/2024] EG MALL Mr Lo: Look for me @EG MALL ECONMECH Dart for the drawing
[09:36, 18/03/2024] EG MALL ECONMECH Dart: Column macam lari ow. L20 to lower roof
[09:36, 18/03/2024] EG MALL ECONMECH Dart: Okok

[10:13, 18/03/2024] Azman HKL: 8th floor. Hotel. @EG MALL ECONMECH Dart @~WY . Tolong inform orang kamu. Mereka jalan ikut itu garis hijau. 200 dari dinding. Belanggar itu sama Chiller pipe.


[10:24, 18/03/2024] Azman HKL: 5th floor. TB4. Slab rebar and M&E in progress.

[15:28, 18/03/2024] Azman HKL: 5th floor. TB4. M&E inspection in progress.

[15:33, 18/03/2024] Azman HKL: Electrical and ELV inspection.
[15:53, 18/03/2024] Azman HKL: Inspection done. @Mr. Voo @~nas4rie please proceed.
[15:54, 18/03/2024] Mr. Voo: 👍🏻