16 MAC 2024 HKL

SITE EG MALL


[08:34, 16/03/2024] Azman HKL: Site progress photo. 16/3/24.
17th floor. TA2. Column and lift rebar in progress.

[08:34, 16/03/2024] Azman HKL: 5th floor. TB4. Slab formwork in progress.


[08:34, 16/03/2024] Azman HKL: 3rd floor. TB6. ST2 RC wall formwork in progress. Lift rebar in progress.

[08:35, 16/03/2024] Azman HKL: Basement. Earthwork in progress.


[11:20, 16/03/2024] +60 19-871 1328: Slmt pagi tuan
[11:20, 16/03/2024] +60 19-871 1328: Minta maaf kelmarin terlupa info kamu pasal ini laluan gas pipe melalui depan lif lobby tidak dibenarkan dalam peraturan ST selain isu bilik gas bawah ramp.. Bolehkah kami ubah laluannya seperti tanda line merah ini??? Nanti tolong update saya.. Ok
[11:20, 16/03/2024] +60 19-871 1328: @Azman HKL @πŸ‘†
[11:22, 16/03/2024] +60 19-871 1328: Untuk bilik gas bawah ramp perlu cari lokasi baru  saja..ok
[11:24, 16/03/2024] Azman HKL: Pipe size 50mm kan. Laluan ini nanti saya double check di drawing dan site. Itu LPG room, tolong cek lokasi baru yang sesuai supaya kita proposed. Saya boleh buka satu RFI ke konsultan berkenaan.

[16:18, 16/03/2024] +60 19-871 1328: @Azman HKL tuan.. Bolehkah kalau kami cadang ini gasroom baru??πŸ‘†
[16:25, 16/03/2024] Azman HKL: Nanti kita proposed.
[16:26, 16/03/2024] Azman HKL: Untuk makluman, next Thursday ada site progress meeting. Semua wakil NSC perlu hadir. 3pm, Site meeting room. 1st floor.
[16:33, 16/03/2024] +60 19-871 1328: NSC office di sana jugakah???
[16:37, 16/03/2024] Azman HKL: 1st floor. Bawah site office HKL.

NSC GROUP 

[08:33, 16/03/2024] Azman HKL: Site progress photo. 16/3/24.
17th floor. TA2. Column and lift rebar in progress.

[08:33, 16/03/2024] Azman HKL: 18th floor. TA1. Slab/beam support in progress.

[08:33, 16/03/2024] Azman HKL: 5th floor. TB4. Slab formwork in progress.

[08:33, 16/03/2024] Azman HKL: 3rd floor. TB6. ST2 RC wall formwork in progress. Lift rebar in progress.

[08:33, 16/03/2024] Azman HKL: Basement. Earthwork in progress.

[09:52, 16/03/2024] Azman HKL: Basement fire tank. Tank installation in progress.

[09:52, 16/03/2024] Azman HKL: Tank installation in progress.
[09:57, 16/03/2024] +60 12-559 6863: @Azman HKL atur sama kai dan Joseph kasi tutup itu wall dan siapkan plaster

[10:06, 16/03/2024] Azman HKL: @~WY ini sampah lepas kerja kasi bersih kumpul. Buang satu kali. Jangan nampak begini. πŸ™petang nanti mesti clear ni ya. πŸ™
[10:06, 16/03/2024] Azman HKL: Iya saya atur.
[11:03, 16/03/2024] +60 19-871 1328: Slmt pagi tuan
[11:11, 16/03/2024] +60 19-871 1328: Minta maaf kelmarin terlupa info kamu pasal ini laluan gas pipe melalui depan lif lobby tidak dibenarkan dalam peraturan ST selain isu bilik gas bawah ramp.. Bolehkah kami ubah laluannya seperti tanda line merah ini??? Nanti tolong update saya.. Ok
[11:14, 16/03/2024] +60 19-871 1328: @Azman HKL @πŸ‘†
[11:16, 16/03/2024] Azman HKL: Selamat Pagi. Boleh post semula dalam wasap group Coordination. Di sana kita bincang dengan consultant. πŸ™

[11:20, 16/03/2024] Azman HKL: Mitsubishi, King Hong, Econmech, DCC. Return shopdrawing from PSM. Boleh collect di site office hari ini atau isnin.πŸ‘†

[14:27, 16/03/2024] Azman HKL: 1st floor. Escalator assembling











 