[09:19, 12/03/2024] Azman HKL: @~Dart 7090 π²πΎ @~LO KEAM . We are here. Basement.
[09:20, 12/03/2024] +60 19-895 9900: Bro, otw ,ada sikit lewatππ»ππ»ππ»ππ»aori
[09:23, 12/03/2024] Azman HKL: π
[10:57, 12/03/2024] Azman HKL: 17th floor. TA1. Request for M&E inspection at 2pm. @Kadapi J. PROMES . NSC site PIC please stand by the site during inspection. π
[11:09, 12/03/2024] Azman HKL: Hotel - Office 8th - 9th floor. @~Julian Kloneles @King Hong Office @~Dart 7090 π²πΎ please check if any comment so we can proceed.
[11:11, 12/03/2024] Azman HKL: Please Comment if any.
NSC GROUP
[10:04, 12/03/2024] Azman HKL: Ducting route.
[10:34, 12/03/2024] Azman HKL: As per discussion, ECM will shift their sprinkler pipe and ducting at the basement. π
[14:10, 12/03/2024] Azman HKL: Site progress photo.
12/3/24.
17th floor, TA1. Slab rebar and M&E in progress
[14:10, 12/03/2024] Azman HKL: 3rd floor, TB6. Slab formwork and rebar in progress
[14:10, 12/03/2024] Azman HKL: 5th floor, TB4, slab formwork in progress.
[14:14, 12/03/2024] Azman HKL: Ground floor, escalator pit repair & touchup work in progress.
[15:02, 12/03/2024] Azman HKL: 17th floor. M&E slab inspection in progress.
[15:45, 12/03/2024] Azman HKL: 17th floor. TA1. Inspection with some comments. 3nos of ACMV pipe sleeve installation is ongoing. Can proceed after it's done. @~Rimon Joseph ambil gambar selepas siap pasang. Lain2 inspection done.